5954-5956 N SIMPSON AVE 91607

Certificate Information: 5954-5956 N SIMPSON AVE 91607

Application / Permit
25014-20000-00798
Plan Check / Job No.
B25VN04669
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
MAJOR REMODEL TO REMOVE CARPORT AND ADDITIONS TO CREATE A (N) 2-STORY 38'-8" x 45'-1" SFD AT 1ST FLOOR AND 2ND DWELLING UNIT AT 2ND FLOOR PER SB9 TWO-UNIT DEVELOPMENT WITH 4'-11" BALCONY PER ENGINEERING. NFPA-13 FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 5/12/2025
Issuing Office
Current Status
Issued on 5/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/21/2025 APPLICANT
Assigned to Plan Check Engineer 2/27/2025 ALFRED RAMIREZ
Assigned to Zoning Architect 2/27/2025 CALEB WONG
Corrections Issued 3/11/2025 ALFRED RAMIREZ
Quality Review Completed 3/11/2025 STEVEN KIM
Building Plans Picked Up 3/11/2025 APPLICANT
Plan Check Approved 5/12/2025 ALFRED RAMIREZ
Issued 5/12/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/18/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/18/2025 LEE GUILBEAUX
CPC Cleared 3/20/2025 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 3/20/2025 LEE GUILBEAUX
Sewer availability Cleared 3/20/2025 LEE GUILBEAUX
Low Impact Development (LID) Cleared 3/27/2025 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 4/1/2025 LEE GUILBEAUX
Senate Bill 9 Cleared 4/24/2025 BRENNEN OBETO
Zoning Plan Check Cleared 5/12/2025 CALEB WONG

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/8/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 8/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/1/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/26/2025 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/30/2025 Conditional Approval JOSE AVILA
Sewer 1/29/2026 Approved JAVIER RAMOS JR
Underground Mechanical 1/29/2026 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 2/9/2026 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 2/9/2026 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/9/2026 Approved JAVIER RAMOS JR
Green Building Rough 2/9/2026 Approved JAVIER RAMOS JR
HVAC-Rough 2/9/2026 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 2/9/2026 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 2/9/2026 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 2/9/2026 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/17/2026 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 2/17/2026 Approved KEVIN BERBERYAN
HVAC-Rough 2/17/2026 Approved KEVIN BERBERYAN
Insulation 2/23/2026 Approved DAVID ANDERSON
Shower Pan 2/23/2026 Approved DAVID ANDERSON
Drywall Nailing 3/3/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 3/3/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 6/11/2026 Approved GAREN HAYRAPETYAN
Gas Test 6/11/2026 Approved GAREN HAYRAPETYAN
HVAC-Final 6/25/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 6/25/2026 Approved GAREN HAYRAPETYAN