3726 1/2 W 59TH ST 90043
Certificate Information: 3726 1/2 W 59TH ST 90043
- Application / Permit
- 25014-20000-00785
- Plan Check / Job No.
- B25VN04561
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 5/1/2025
- Issuing Office
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 2/25/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/27/2025 | APPLICANT |
| Plan Check Approved | 4/25/2025 | GIOVANNY CHAVEZ |
| Issued | 5/1/2025 | APPLICANT |
| CofO in Progress | 1/21/2026 | SCOTT FINNILA |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
| CofO Issued | 1/21/2026 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 3/3/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2025 | WALLIE JONG |
| Sewer availability | Cleared | 3/12/2025 | WALLIE JONG |
| Construction near power lines | Cleared | 4/24/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/24/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Rc Building Group Co; Lic. No.: 1023300-B | 11938 LAMBERT EL MONTE, CA 91732 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/20/2025 | Corrections Issued | WAYNE REGESTER |
| Excavation/Setback/Form/Re-Bar | 5/23/2025 | Approved | WAYNE REGESTER |
| Footing/Foundation/Slab | 5/23/2025 | Approved | WAYNE REGESTER |
| Sewer | 5/23/2025 | Approved | WAYNE REGESTER |
| Underground Mechanical | 5/23/2025 | Approved | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Corrections Issued | BARRY HACHE |
| Deputy Wood Construction | 6/11/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 6/12/2025 | Approved | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 6/12/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 6/12/2025 | Approved | WAYNE REGESTER |
| Insulation | 6/17/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 6/17/2025 | Approved | WAYNE REGESTER |
| Shower Pan | 6/17/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 6/20/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 6/20/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 6/20/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 8/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 8/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 8/29/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 8/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 8/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 8/29/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 1/16/2026 | Approved | SCOTT FINNILA |
| Final | 1/16/2026 | OK to Issue CofO | SCOTT FINNILA |
| HVAC-Final | 1/16/2026 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 1/16/2026 | Approved | SCOTT FINNILA |