6928-6930 N ENFIELD AVE 91335

Certificate Information: 6928-6930 N ENFIELD AVE 91335

Application / Permit
25014-20000-00781
Plan Check / Job No.
B25VN04533
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF (E) SFD TO 791 SQ.FT ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) AND ADD 6'-0" X 16'-6" PATIO.
Permit Issued
Issued on 3/10/2025
Issuing Office
Valley
Current Status
CofO Issued on 11/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2025 APPLICANT
Assigned to Plan Check Engineer 2/26/2025 ARTIN ZARUKIAN
Corrections Issued 3/3/2025 ARTIN ZARUKIAN
Building Plans Picked Up 3/3/2025 APPLICANT
Plan Check Approved 3/10/2025 OMAR GARNICA
Issued 3/10/2025 APPLICANT
CofO in Progress 10/29/2025 ARUTYUN MADATYAN
Permit Finaled 11/10/2025 JOHN JANSON
CofO Issued 11/10/2025 JOHN JANSON
Permit Finaled 11/10/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/5/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/5/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 3/5/2025 RYAN CASTRO
Sewer availability Cleared 3/5/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/21/2025 Approved JUAN ALVARADO
HVAC-Rough 3/21/2025 Approved JUAN ALVARADO
PLUMBING-Rough 3/21/2025 Approved JUAN ALVARADO
Underground Mechanical 3/21/2025 Approved JUAN ALVARADO
Deputy Drilled-In Anchors 4/2/2025 Conditional Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 4/7/2025 Not Ready for Inspection JUAN ALVARADO
Footing/Foundation/Slab 4/7/2025 Approved JUAN ALVARADO
Green Building Rough 4/7/2025 Approved JUAN ALVARADO
Insulation 4/15/2025 Approved JUAN ALVARADO
Drywall Nailing 4/23/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 5/5/2025 Approved JUAN ALVARADO
Shower Pan 5/5/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 7/2/2025 Approved JUAN ALVARADO
ELECTRICAL-Final 7/2/2025 Approved JUAN ALVARADO
Final 7/2/2025 Corrections Issued JUAN ALVARADO
Gas Test 7/2/2025 Approved JUAN ALVARADO
Green Building Final 7/2/2025 Approved JUAN ALVARADO
HVAC-Final 7/2/2025 Not Ready for Inspection JUAN ALVARADO
PLUMBING-Final 7/2/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Not Ready JUAN ALVARADO
Service/Power Release 7/2/2025 Not Ready for Inspection JUAN ALVARADO
Smoke Detectors 7/2/2025 Approved JUAN ALVARADO
Final 8/1/2025 Corrections Issued JUAN ALVARADO
HVAC-Final 8/1/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Approved JUAN ALVARADO
Footing/Foundation/Slab 10/23/2025 Partial Approval ARUTYUN MADATYAN
Service/Power Release 10/23/2025 Approved ARUTYUN MADATYAN
Final 10/29/2025 OK to Issue CofO ARUTYUN MADATYAN
Footing/Foundation/Slab 10/29/2025 Approved ARUTYUN MADATYAN