5658-5660 N VALLEY CIRCLE BLVD 91367
Certificate Information: 5658-5660 N VALLEY CIRCLE BLVD 91367
- Application / Permit
- 25014-20000-00777
- Plan Check / Job No.
- B25VN04519
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e).
- Permit Issued
- Issued on 5/29/2025
- Issuing Office
- Current Status
- Issued on 5/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 2/27/2025 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 3/24/2025 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/3/2025 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 4/6/2025 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 4/10/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 4/21/2025 | MOHAMMAD ESMAILI |
| Issued | 5/29/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 2/28/2025 | EDGAR ALCARAZ |
| Grading Pre-Inspection | Cleared | 3/4/2025 | ROBERT PINA |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 3/5/2025 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hagopyan,, Edmond; Lic. No.: C80143 | 3300 FOOTHILL BLVD # 8601 GLENDALE, CA 91214 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/4/2026 | Partial Approval | GEVORK IPCHYAN |
| Sewer | 2/4/2026 | Partial Approval | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 2/11/2026 | Corrections Issued | GEVORK IPCHYAN |
| Deputy Drilled-In Anchors | 2/12/2026 | Conditional Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 2/13/2026 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 3/12/2026 | Corrections Issued | GEVORK IPCHYAN |
| Deputy Drilled-In Anchors | 3/17/2026 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 4/1/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 4/1/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Rough | 4/1/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Wood Frame | 4/1/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2026 | Partial Approval | GEVORK IPCHYAN |
| Rough-Elec/Plmb/HVAC | 4/14/2026 | Partial Approval | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 4/23/2026 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 4/23/2026 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/23/2026 | Partial Approval | GEVORK IPCHYAN |
| Rough-Elec/Plmb/HVAC | 4/23/2026 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 5/1/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Shower Pan | 5/1/2026 | Approved | JUAN ALVARADO |
| Drywall Nailing | 5/6/2026 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 5/6/2026 | Partial Approval | GEVORK IPCHYAN |