10918 W OAK MOUNTAIN PL 91040

Certificate Information: 10918 W OAK MOUNTAIN PL 91040

Application / Permit
25014-20000-00770
Plan Check / Job No.
B25VN04459
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED ACCESSORY LIVING QUARTERS AND NEW ADDITION TO NEW ACCESSORY DWELLING UNIT PER GCS 66323(a)(2). EXISTING ATTACHED PATIO COVER TO REMAIN. NFPA-13D FIRE SPRINKLERS TO BE INSTALLED.
Permit Issued
Issued on 4/8/2025
Issuing Office
Valley
Current Status
CofO Issued on 5/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2025 APPLICANT
Assigned to Plan Check Engineer 2/24/2025 ARTIN ZARUKIAN
Corrections Issued 2/24/2025 ARTIN ZARUKIAN
Building Plans Picked Up 2/27/2025 APPLICANT
Applicant returned to address corrections 3/26/2025 MOHAMMAD ESMAILI
Plan Check Approved 4/8/2025 MADISON O'DELL
Issued 4/8/2025 APPLICANT
CofO in Progress 4/21/2026 DAVID ANDERSON
Permit Finaled 5/11/2026 RUBEN SALAS
CofO Issued 5/11/2026 RUBEN SALAS
Permit Finaled 5/11/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/10/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/10/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/10/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/11/2025 TREVOR QUAN
Sewer availability Cleared 3/11/2025 TREVOR QUAN
Hydrant and Access approval Cleared 3/12/2025 RUEL COLE
Specific Plan Cleared 3/25/2025 JOSHUA ORDONEZ
Grading Pre-Inspection Cleared 4/8/2025 ROBERT PINA

Contact Information

Contractor Green Planet Restoration Of La; Lic. No.: 1009639-ASB 9146 OWENSMOUTH AVE      CHATSWORTH, CA 91311
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/10/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 7/10/2025 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 10/30/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Approved DAVID ANDERSON
PLUMBING-Rough 10/30/2025 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 11/14/2025 Approved DAVID ANDERSON
Green Building Rough 11/14/2025 Approved DAVID ANDERSON
HVAC-Rough 11/14/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/14/2025 Partial Approval DAVID ANDERSON
PLUMBING-Rough 11/14/2025 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 11/14/2025 Approved DAVID ANDERSON
Drywall Nailing 11/18/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/18/2025 Approved DAVID ANDERSON
Final 1/23/2026 Corrections Issued NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 1/23/2026 Approved NICHOLAS TROWBRIDGE
Green Building Final 1/23/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 1/23/2026 SGSOV Approved NICHOLAS TROWBRIDGE
Smoke Detectors 1/23/2026 Approved NICHOLAS TROWBRIDGE
Final 3/25/2026 Corrections Issued DAVID ANDERSON
Green Building Final 3/25/2026 Approved DAVID ANDERSON
Final 4/8/2026 OK to Issue CofO DAVID ANDERSON