4248 N FARMDALE AVE 91604
Certificate Information: 4248 N FARMDALE AVE 91604
- Application / Permit
- 25014-20000-00762
- Plan Check / Job No.
- B25VN04417
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: addition to and convert (E) detached garage into ADU per GC66323(a)(2)
- Permit Issued
- Issued on 5/5/2025
- Issuing Office
- Current Status
- CofO Issued on 12/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2025 | JOHNPAUL ISIP |
| Corrections Issued | 2/26/2025 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 3/20/2025 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 4/18/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 4/30/2025 | JOHNPAUL ISIP |
| Issued | 5/5/2025 | APPLICANT |
| CofO in Progress | 12/8/2025 | JAVIER RAMOS JR |
| Permit Finaled | 12/16/2025 | RUBEN SALAS |
| CofO Issued | 12/16/2025 | RUBEN SALAS |
| Permit Finaled | 12/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 3/6/2025 | DORIAN AGUILAR |
| Address approval | Cleared | 3/7/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/7/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/18/2025 | BIAINA HARITUNIAN |
Contact Information
| Architect | Perella,, Ryan Adam; Lic. No.: NA30833 | , |
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel H; Lic. No.: NA67905 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 9/18/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/18/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 9/18/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/18/2025 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 9/19/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/25/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/25/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/25/2025 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/25/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/25/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/25/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/29/2025 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 9/29/2025 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/29/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 9/29/2025 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 9/29/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/3/2025 | Approved | LOUIS ESCOTO |
| Insulation | 10/3/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 11/20/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/20/2025 | Partial Inspection | JAVIER RAMOS JR |
| Final | 11/20/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 11/20/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 11/20/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 11/20/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Not Required | JAVIER RAMOS JR |
| Smoke Detectors | 11/20/2025 | Approved | JAVIER RAMOS JR |
| Green Building Final | 11/24/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/25/2025 | Approved | JAVIER RAMOS JR |
| Final | 11/25/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 12/8/2025 | OK to Issue CofO | JAVIER RAMOS JR |