7671 N QUAKERTOWN AVE 91306

Certificate Information: 7671 N QUAKERTOWN AVE 91306

Application / Permit
25014-20000-00734
Plan Check / Job No.
B25VN04206
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE AND NEW ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). RE-FRAME ENTIRE ROOF. WORK DONE PER WFPP.
Permit Issued
Issued on 5/9/2025
Issuing Office
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Plan Check Engineer 2/21/2025 MADISON ODELL
Corrections Issued 2/22/2025 MADISON ODELL
Applicant returned to address corrections 3/26/2025 MADISON ODELL
Plan Check Approved 5/9/2025 ALEC MOUSAKHANIAN
Issued 5/9/2025 APPLICANT
CofO in Progress 12/23/2025 ALEXANDER HANDY
Permit Finaled 1/2/2026 JOHN JANSON
CofO Issued 1/2/2026 JOHN JANSON
Permit Finaled 1/2/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/27/2025 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 3/24/2025 CARLOS AGUILERA
Sewer availability Cleared 3/24/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/29/2025 CARLOS AGUILERA
Construction near power lines Cleared 4/15/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/6/2025 Partial Approval ALEXANDER HANDY
Footing/Foundation/Slab 6/23/2025 Corrections Issued SCOTT SOBEL
Deputy Drilled-In Anchors 6/24/2025 Conditional Approval HENRY KIM
Footing/Foundation/Slab 6/30/2025 Corrections Issued SCOTT SOBEL
Footing/Foundation/Slab 7/3/2025 Not Ready for Inspection SCOTT SOBEL
PLUMBING-Rough 7/3/2025 Partial Approval SCOTT SOBEL
Deputy Other (see comments) 7/12/2025 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 7/12/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Approved ALEXANDER HANDY
Green Building Rough 7/21/2025 Not Ready for Inspection ALEXANDER HANDY
Interior/Exterior Lathing 9/3/2025 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 9/3/2025 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 9/9/2025 Approved ALEXANDER HANDY
ELECTRICAL-Rough 9/9/2025 Approved ALEXANDER HANDY
Green Building Rough 9/9/2025 Approved ALEXANDER HANDY
HVAC-Rough 9/9/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 9/9/2025 Approved ALEXANDER HANDY
Insulation 9/11/2025 Conditional Approval GEVORK IPCHYAN
Shower Pan 9/11/2025 Approved GEVORK IPCHYAN
Drywall Nailing 9/19/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 9/19/2025 Partial Approval KRISTEN CAUSEY
ELECTRICAL-Final 12/9/2025 Not Ready for Inspection JON MCHUGH
Final 12/9/2025 Corrections Issued JON MCHUGH
Green Building Final 12/9/2025 Approved JON MCHUGH
HVAC-Final 12/9/2025 Not Ready for Inspection JON MCHUGH
PLUMBING-Final 12/9/2025 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Approved JON MCHUGH
Service/Power Release 12/9/2025 Not Ready for Inspection JON MCHUGH
Smoke Detectors 12/9/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 12/18/2025 Approved ALEXANDER HANDY
Final 12/18/2025 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 12/18/2025 Approved ALEXANDER HANDY
PLUMBING-Final 12/18/2025 Approved ALEXANDER HANDY
Service/Power Release 12/18/2025 Approved ALEXANDER HANDY
Smoke Detectors 12/18/2025 Approved ALEXANDER HANDY