11227 1/2 W KLING ST 91602
Certificate Information: 11227 1/2 W KLING ST 91602
- Application / Permit
- 25014-20000-00719
- Plan Check / Job No.
- B25VN04154
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & ADD 2-STORIES
- Permit Issued
- Issued on 3/25/2025
- Issuing Office
- Current Status
- CofO Issued on 11/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2025 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/6/2025 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/6/2025 | JASON HEALEY |
| Building Plans Picked Up | 3/10/2025 | APPLICANT |
| Applicant returned to address corrections | 3/20/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/25/2025 | NILOOFAR MEHRAIN |
| Issued | 3/25/2025 | APPLICANT |
| CofO in Progress | 9/17/2025 | JAVIER RAMOS JR |
| Permit Finaled | 11/19/2025 | RUBEN SALAS |
| CofO Issued | 11/19/2025 | RUBEN SALAS |
| Permit Finaled | 11/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 3/7/2025 | WALLIE JONG |
| Sewer availability | Cleared | 3/7/2025 | WALLIE JONG |
Contact Information
| Contractor | Az Vision Remodeling; Lic. No.: 1015050-B | 11909 TIARA STREET VALLEY VILLAGE, CA 91607 |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/10/2025 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 4/11/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/15/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Wood Frame | 4/23/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Deputy Wood Construction | 5/14/2025 | Conditional Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/30/2025 | Approved | JAVIER RAMOS JR |
| Sewer | 5/30/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Sewer | 6/3/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 6/3/2025 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/4/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/4/2025 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 6/4/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/4/2025 | Corrections Issued | JAVIER RAMOS JR |
| MERV13>=Rough | 6/4/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/16/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/16/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/24/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/24/2025 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 7/1/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 7/3/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 7/3/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 7/8/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 9/4/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/4/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 9/4/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 9/4/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 9/4/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 9/4/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 9/4/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 9/4/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/16/2025 | OK to Issue CofO | JAVIER RAMOS JR |