11227 1/2 W KLING ST 91602

Certificate Information: 11227 1/2 W KLING ST 91602

Application / Permit
25014-20000-00719
Plan Check / Job No.
B25VN04154
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & ADD 2-STORIES
Permit Issued
Issued on 3/25/2025
Issuing Office
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Plan Check Engineer 2/20/2025 NILOOFAR MEHRAIN
Corrections Issued 3/6/2025 NILOOFAR MEHRAIN
Quality Review Completed 3/6/2025 JASON HEALEY
Building Plans Picked Up 3/10/2025 APPLICANT
Applicant returned to address corrections 3/20/2025 NILOOFAR MEHRAIN
Plan Check Approved 3/25/2025 NILOOFAR MEHRAIN
Issued 3/25/2025 APPLICANT
CofO in Progress 9/17/2025 JAVIER RAMOS JR
Permit Finaled 11/19/2025 RUBEN SALAS
CofO Issued 11/19/2025 RUBEN SALAS
Permit Finaled 11/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/7/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/7/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 3/7/2025 WALLIE JONG
Sewer availability Cleared 3/7/2025 WALLIE JONG

Contact Information

Contractor Az Vision Remodeling; Lic. No.: 1015050-B 11909 TIARA STREET      VALLEY VILLAGE, CA 91607
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/10/2025 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 4/11/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/15/2025 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Not Ready for Inspection JUAN VALENZUELA
Wood Frame 4/23/2025 Not Ready for Inspection JUAN VALENZUELA
Deputy Wood Construction 5/14/2025 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 5/30/2025 Approved JAVIER RAMOS JR
Sewer 5/30/2025 Not Ready for Inspection JAVIER RAMOS JR
Sewer 6/3/2025 Approved JAVIER RAMOS JR
Underground Mechanical 6/3/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 6/4/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 6/4/2025 Approved JAVIER RAMOS JR
Green Building Rough 6/4/2025 Approved JAVIER RAMOS JR
HVAC-Rough 6/4/2025 Corrections Issued JAVIER RAMOS JR
MERV13>=Rough 6/4/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 6/16/2025 Approved JAVIER RAMOS JR
HVAC-Rough 6/16/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/24/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/24/2025 Partial Approval JAVIER RAMOS JR
Insulation 7/1/2025 Approved LOUIS ESCOTO
Drywall Nailing 7/3/2025 Approved LOUIS ESCOTO
Shower Pan 7/3/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 7/8/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 9/4/2025 Approved JAVIER RAMOS JR
Final 9/4/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 9/4/2025 Approved JAVIER RAMOS JR
HVAC-Final 9/4/2025 Approved JAVIER RAMOS JR
MERV13>=Final 9/4/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 9/4/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/4/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 9/4/2025 Approved JAVIER RAMOS JR
Smoke Detectors 9/4/2025 Approved JAVIER RAMOS JR
Final 9/16/2025 OK to Issue CofO JAVIER RAMOS JR