5416 N WHITSETT AVE 91607
Certificate Information: 5416 N WHITSETT AVE 91607
- Application / Permit
- 25014-20000-00708
- Plan Check / Job No.
- B25VN04104
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (4) Bathhouse and Plunge
- Work Description
- EPLAN: CHANGE OF USE FROM EXISTING 54'1-1/2" X 43'8" (2,332 SQ.FT. ) RESTAURANT TO A TURKISH BATH MIKVAH AND NEW IRREGULAR SHAPED ONE STORY ADDITION , NFPA-13 FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/17/2026
- Issuing Office
- Current Status
- Issued on 3/17/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | RARES BODEA |
| Assigned to Zoning Architect | 2/27/2025 | CALEB WONG |
| Corrections Issued | 3/3/2025 | RARES BODEA |
| Quality Review Completed | 3/4/2025 | STEVEN KIM |
| Applicant returned to address corrections | 5/19/2025 | RARES BODEA |
| Applicant returned to address corrections | 6/16/2025 | RARES BODEA |
| Applicant returned to address corrections | 2/25/2026 | RARES BODEA |
| Applicant returned to address corrections | 3/9/2026 | RARES BODEA |
| Plan Check Approved | 3/17/2026 | RARES BODEA |
| Issued | 3/17/2026 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/7/2025 | JACQUELINE TORRES |
| ZA Case | Cleared | 3/7/2025 | JACQUELINE TORRES |
| "Q" conditions | Cleared | 3/11/2025 | JACQUELINE TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/4/2025 | CARLOS AGUILERA |
| Specific Plan | Cleared | 4/16/2025 | SASHA KASSAB |
| Trees in Parkway | Cleared | 4/18/2025 | MIGUEL ORNELAS |
| Green Code | Cleared | 6/4/2025 | MICHAEL AYERS |
| DAS Clearance | Cleared | 7/22/2025 | Sergio Muniz |
| Permit | Cleared | 2/2/2026 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 2/3/2026 | JESUS CISNEROS |
| Highway dedication | Cleared | 2/17/2026 | DAVID LOPEZ |
| Zoning Plan Check | Cleared | 2/17/2026 | CALEB WONG |
Contact Information
| Contractor | Yay Construction Inc; Lic. No.: 1078903-B | , |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 375 LA MIRADA AVENUE SAN MARINO, CA 91108 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 3/24/2026 | Corrections Issued | JEFFREY FULTON |
| Wood Frame | 3/24/2026 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 4/14/2026 | Conditional Approval | JEFFREY FULTON |
| Footing/Foundation/Slab | 6/10/2026 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Reinf. Concrete | 6/12/2026 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 6/12/2026 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 6/24/2026 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 6/30/2026 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 6/30/2026 | Not Ready for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 7/6/2026 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Deputy Drilled-In Anchors | 7/7/2026 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 7/22/2026 | Approved | ROBERT DAVIS |