22850 W LULL ST 91304
Certificate Information: 22850 W LULL ST 91304
- Application / Permit
- 25014-20000-00706
- Plan Check / Job No.
- B25VN04092
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, 37' X 22' IRREGULAR SHAPED ADDITION TO (E) SFD. ALL WORK PER ENG.
- Permit Issued
- Issued on 4/14/2025
- Issuing Office
- Valley
- Current Status
- Issued on 4/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 2/22/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 2/24/2025 | APPLICANT |
| Applicant returned to address corrections | 3/6/2025 | ARAMIK SHAHMIRZAIAN |
| Applicant returned to address corrections | 3/11/2025 | YAQUB MIRZA |
| Issued | 4/14/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/24/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/24/2025 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 4/11/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Fox Construction; Lic. No.: 1014686-B | 15402 VOSE ST VAN NUYS, CA 91406 |
| Engineer | Basseri,, Siavash M; Lic. No.: C45487 | 5250 W CENTURY BLVD STE 300 LOS ANGELES, CA 90045 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/22/2025 | Partial Approval | JEFFREY HARTLINE |
| Underground Mechanical | 5/1/2025 | Approved | JEFFREY HARTLINE |
| Deputy Drilled-In Anchors | 5/5/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/5/2025 | Approved | JOHN COLEMAN |
| Sewer | 5/5/2025 | Approved | JOHN COLEMAN |
| Deputy Drilled-In Anchors | 6/18/2025 | Conditional Approval | HENRY KIM |
| BUILDING-Rough-Frame | 6/20/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2025 | Partial Approval | GEVORK IPCHYAN |
| Green Building Rough | 6/20/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Wood Frame | 6/20/2025 | Partial Approval | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 7/7/2025 | Partial Approval | GEVORK IPCHYAN |
| Rough-Elec/Plmb/HVAC | 7/7/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Shower Pan | 7/7/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 7/9/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Rough | 7/9/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 7/9/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 7/10/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 7/10/2025 | Partial Approval | JEFFREY HARTLINE |
| Insulation | 7/11/2025 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 7/15/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Drywall Nailing | 7/15/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 7/15/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Partial Approval | JEFFREY HARTLINE |
| Green Building Final | 7/15/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Rough | 7/15/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Not Ready | JEFFREY HARTLINE |
| Smoke Detectors | 7/15/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 7/17/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 7/21/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 7/25/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Drywall Nailing | 7/28/2025 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/28/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 10/3/2025 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Final | 12/15/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 12/15/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Final | 12/15/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| HVAC-Final | 12/15/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Final | 12/15/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/15/2025 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 12/15/2025 | Approved | JEFFREY HARTLINE |