13036 N MEADOWLARK AVE 91344

Certificate Information: 13036 N MEADOWLARK AVE 91344

Application / Permit
25014-20000-00629
Plan Check / Job No.
B25VN03583
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. (N) Addition to (E) Single Family Dwelling w/ attach Accessory Dwelling Unit per WFPP
Permit Issued
Issued on 3/27/2025
Issuing Office
Current Status
CofO Issued on 5/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2025 APPLICANT
Assigned to Plan Check Engineer 2/20/2025 AMY GUEVARRA
Corrections Issued 2/23/2025 AMY GUEVARRA
Applicant returned to address corrections 3/20/2025 AMY GUEVARRA
Plan Check Approved 3/27/2025 AMY GUEVARRA
Issued 3/27/2025 APPLICANT
CofO in Progress 5/20/2026 STEVEN BACK
Permit Finaled 5/22/2026 JOHN JANSON
CofO Issued 5/22/2026 JOHN JANSON
Permit Finaled 5/22/2026 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/25/2025 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 2/25/2025 GERMAN RODRIGUEZ MENDOZA
Eng Process Fee Ord 176,300 Cleared 2/27/2025 SAFA JAVANMARDI
Sewer availability Cleared 3/11/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 7/14/2025 Partial Approval STEVEN BACK
PLUMBING-Rough 7/29/2025 Partial Approval STEVEN BACK
Deputy Drilled-In Anchors 8/13/2025 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 8/15/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 9/25/2025 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 9/25/2025 Partial Approval DAVID SCANTLIN
Sewer 9/25/2025 Approved DAVID SCANTLIN
Deputy Wood Construction 9/26/2025 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 10/2/2025 Partial Approval DAVID SCANTLIN
Green Building Rough 10/2/2025 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 10/29/2025 Corrections Issued STEVEN BACK
PLUMBING-Rough 10/29/2025 Approved STEVEN BACK
Shower Pan 10/29/2025 Approved STEVEN BACK
ELECTRICAL-Rough 12/5/2025 Not Ready for Inspection HENRY KIM
Interior/Exterior Lathing 12/5/2025 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 12/31/2025 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 12/31/2025 Approved STEVEN BACK
HVAC-Rough 12/31/2025 Approved STEVEN BACK
BUILDING-Rough-Frame 1/2/2026 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 1/2/2026 Approved STEVEN BACK
Green Building Rough 1/2/2026 Approved STEVEN BACK
BUILDING-Rough-Frame 1/7/2026 Approved JEFFREY PARD
Insulation 1/8/2026 Approved DAVID SCANTLIN
Drywall Nailing 1/22/2026 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/22/2026 Partial Approval DAVID SCANTLIN
Interior/Exterior Lathing 1/27/2026 Approved STEVEN BACK
Final 4/29/2026 Corrections Issued STEVEN BACK
Green Building Final 4/29/2026 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 4/29/2026 SGSOV Approved STEVEN BACK
Smoke Detectors 4/29/2026 Approved STEVEN BACK
Final 5/20/2026 Conditional Approval STEVEN BACK