18355 W ARMINTA ST 91335

Certificate Information: 18355 W ARMINTA ST 91335

Application / Permit
25014-20000-00619
Plan Check / Job No.
B25VN03535
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF A NEW BEDROOM AND BATHROOM TO THE (E) SFD.
Permit Issued
Issued on 2/12/2025
Issuing Office
Valley
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2025 APPLICANT
Assigned to Plan Check Engineer 2/11/2025 ALEC MOUSAKHANIAN
Corrections Issued 2/11/2025 ALEC MOUSAKHANIAN
Applicant returned to address corrections 2/11/2025 ALEC MOUSAKHANIAN
Plan Check Approved 2/12/2025 ALEC MOUSAKHANIAN
Issued 2/12/2025 APPLICANT
CofO in Progress 7/29/2025 JUAN ALVARADO
Permit Finaled 8/29/2025 JOHN JANSON
CofO Issued 8/29/2025 JOHN JANSON
Permit Finaled 8/29/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/12/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 2/12/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/12/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/11/2025 Conditional Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 3/13/2025 Not Ready for Inspection JUAN ALVARADO
PLUMBING-Rough 3/13/2025 Approved JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 3/17/2025 Approved JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 5/2/2025 Not Ready for Inspection JUAN ALVARADO
ELECTRICAL-Rough 5/2/2025 Not Ready for Inspection JUAN ALVARADO
PLUMBING-Rough 5/2/2025 Corrections Issued JUAN ALVARADO
BUILDING-Rough-Frame 5/7/2025 Approved JUAN ALVARADO
ELECTRICAL-Rough 5/7/2025 Approved JUAN ALVARADO
HVAC-Rough 5/7/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 5/7/2025 Approved JUAN ALVARADO
PLUMBING-Rough 5/7/2025 Approved JUAN ALVARADO
Insulation 5/9/2025 Approved JUAN ALVARADO
Drywall Nailing 6/9/2025 Approved JUAN ALVARADO
Shower Pan 6/9/2025 Approved JUAN ALVARADO
ELECTRICAL-Final 7/18/2025 Approved JUAN ALVARADO
Final 7/18/2025 Corrections Issued JUAN ALVARADO
Footing/Foundation/Slab 7/18/2025 Approved JUAN ALVARADO
HVAC-Final 7/18/2025 Approved JUAN ALVARADO
PLUMBING-Final 7/18/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 7/18/2025 SGSOV Approved JUAN ALVARADO
Smoke Detectors 7/18/2025 Approved JUAN ALVARADO
Final 7/28/2025 OK to Issue CofO JUAN ALVARADO