14922 W MAYALL ST 91345

Certificate Information: 14922 W MAYALL ST 91345

Application / Permit
25014-20000-00615
Plan Check / Job No.
B25VN03499
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: ADDITION AT FRONT OF THE BUILDING AND REMODEL
Permit Issued
Issued on 1/7/2026
Issuing Office
Current Status
CofO in Progress on 5/26/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/22/2025 APPLICANT
Assigned to Plan Check Engineer 5/28/2025 MOHAMMAD ESMAILI
Corrections Issued 5/29/2025 MOHAMMAD ESMAILI
Applicant returned to address corrections 12/12/2025 MOHAMMAD ESMAILI
Applicant returned to address corrections 12/18/2025 MOHAMMAD ESMAILI
Applicant returned to address corrections 12/22/2025 MOHAMMAD ESMAILI
Plan Check Approved 1/2/2026 MOHAMMAD ESMAILI
Issued 1/7/2026 APPLICANT
CofO in Progress 5/26/2026 JENNIFER RABUCHIN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/9/2025 TONY CHIANG
Roof/Waste drainage to street Cleared 12/10/2025 TONY CHIANG

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: NA24587       ,
Contractor Aris Contractor Inc; Lic. No.: 909593-B       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/15/2026 Approved JENNIFER RABUCHIN
HVAC-Rough 1/15/2026 Approved JENNIFER RABUCHIN
Insulation 1/15/2026 Approved JENNIFER RABUCHIN
PLUMBING-Rough 1/15/2026 Approved JENNIFER RABUCHIN
Drywall Nailing 2/5/2026 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 2/5/2026 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 3/16/2026 Approved JOSE AVILA
Shower Pan 3/16/2026 Approved JOSE AVILA
BUILDING-Rough-Frame 5/11/2026 Approved JENNIFER RABUCHIN
Final 5/11/2026 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 5/11/2026 Approved JENNIFER RABUCHIN
Green Building Final 5/11/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/11/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/11/2026 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 5/11/2026 Corrections Issued JENNIFER RABUCHIN
Final 5/26/2026 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 5/26/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 5/26/2026 Approved JENNIFER RABUCHIN