14922 W MAYALL ST 91345
Certificate Information: 14922 W MAYALL ST 91345
- Application / Permit
- 25014-20000-00615
- Plan Check / Job No.
- B25VN03499
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: ADDITION AT FRONT OF THE BUILDING AND REMODEL
- Permit Issued
- Issued on 1/7/2026
- Issuing Office
- Current Status
- CofO in Progress on 5/26/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2025 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/29/2025 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 12/12/2025 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 12/18/2025 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 12/22/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 1/2/2026 | MOHAMMAD ESMAILI |
| Issued | 1/7/2026 | APPLICANT |
| CofO in Progress | 5/26/2026 | JENNIFER RABUCHIN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2025 | TONY CHIANG |
| Roof/Waste drainage to street | Cleared | 12/10/2025 | TONY CHIANG |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: NA24587 | , |
| Contractor | Aris Contractor Inc; Lic. No.: 909593-B | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/15/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 1/15/2026 | Approved | JENNIFER RABUCHIN |
| Insulation | 1/15/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/15/2026 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 2/5/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/5/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/16/2026 | Approved | JOSE AVILA |
| Shower Pan | 3/16/2026 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/11/2026 | Approved | JENNIFER RABUCHIN |
| Final | 5/11/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/11/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 5/11/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 5/11/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/11/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 5/11/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 5/26/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/26/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 5/26/2026 | Approved | JENNIFER RABUCHIN |