4928 N WILLOW CREST AVE 91601

Certificate Information: 4928 N WILLOW CREST AVE 91601

Application / Permit
25014-20000-00611
Plan Check / Job No.
B25VN03479
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan. Addition and major remodel to (E) single family dwelling.
Permit Issued
Issued on 3/25/2025
Issuing Office
Current Status
CofO Issued on 4/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 ALEXANDER JOO
Corrections Issued 2/18/2025 ALEXANDER JOO
Quality Review Completed 2/19/2025 GARO TELMI
Applicant returned to address corrections 3/14/2025 ALEXANDER JOO
Applicant returned to address corrections 3/20/2025 ALEXANDER JOO
Plan Check Approved 3/24/2025 ALEXANDER JOO
Issued 3/25/2025 APPLICANT
CofO in Progress 4/8/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 4/28/2026 RUBEN SALAS
CofO Issued 4/28/2026 RUBEN SALAS
Permit Finaled 4/28/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/21/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 3/1/2025 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Gao,, Jianfeng; Lic. No.: C88478 18825 ELMHURST ST      ROWLAND HEIGHTS, CA 91748

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/17/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/26/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 6/26/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 7/24/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 7/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 10/6/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/6/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/6/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 10/8/2025 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 10/8/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/9/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 10/9/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 10/14/2025 Approved MICHAEL CORTEZ
Shower Pan 10/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 10/30/2025 Approved JOSE AVILA
Gas Test 3/4/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 3/4/2026 Approved GAREN HAYRAPETYAN
Final 3/19/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 3/19/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/19/2026 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 3/19/2026 Approved GAREN HAYRAPETYAN
Final 4/8/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ