5807 N CALVIN AVE 91356
Certificate Information: 5807 N CALVIN AVE 91356
- Application / Permit
- 25014-20000-00580
- Plan Check / Job No.
- B25VN03289
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (E) SFD INTERIOR REMODELING. CONVERT PART OF THE (E) PATIO COVER (211 SF) INTO NEW LIVING AREA. (N) 157.5 SF. ADDITION @ REAR PART OF THE HOUSE. INTERIOR REMODELING TO INCLUDE KITCHEN REMODELING, REMOVAL OF LOAD BEARING WALLS, NEW VAULTED CEILING AREAS, NEW WINDOWS AND DOORS.
- Permit Issued
- Issued on 4/7/2025
- Issuing Office
- Current Status
- CofO Issued on 2/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2025 | JOHN MESIAS |
| Corrections Issued | 2/15/2025 | JOHN MESIAS |
| Applicant returned to address corrections | 3/21/2025 | JOHN MESIAS |
| Plan Check Approved | 4/2/2025 | CRYSTEL MAALOUF |
| Issued | 4/7/2025 | APPLICANT |
| CofO in Progress | 1/13/2026 | JON MCHUGH |
| Permit Finaled | 2/25/2026 | JOHN JANSON |
| CofO Issued | 2/25/2026 | JOHN JANSON |
| Permit Finaled | 2/25/2026 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/19/2025 | BIAINA HARITUNIAN |
| ZI | Cleared | 3/20/2025 | JAZMIN ROQUE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/29/2025 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 6/3/2025 | Corrections Issued | JON MCHUGH |
| Special/Order Compliance | 6/3/2025 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Partial Approval | JON MCHUGH |
| Insulation | 6/12/2025 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 7/2/2025 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 7/2/2025 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 7/2/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 7/2/2025 | Approved | JON MCHUGH |
| Green Building Rough | 7/2/2025 | Off-Hour Fees Due | |
| HVAC-Rough | 7/2/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 7/2/2025 | Off-Hour Fees Due | |
| MERV13>=Rough | 7/2/2025 | Off-Hour Fees Due | |
| PLUMBING-Rough | 7/2/2025 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 7/2/2025 | Off-Hour Fees Due | |
| Rough-Elec/Plmb/HVAC | 7/2/2025 | Off-Hour Fees Due | |
| Wood Frame | 7/2/2025 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 7/14/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 7/14/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 7/14/2025 | Partial Approval | JON MCHUGH |
| MERV13>=Rough | 7/14/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 7/14/2025 | Approved | JON MCHUGH |
| Shower Pan | 7/14/2025 | Partial Approval | JON MCHUGH |
| Insulation | 7/21/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 7/21/2025 | Approved | JON MCHUGH |
| Shower Pan | 7/21/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 7/28/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 7/28/2025 | Approved | JON MCHUGH |
| Final | 12/18/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 12/18/2025 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Final | 12/18/2025 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 12/18/2025 | Not Required | JON MCHUGH |
| Smoke Detectors | 12/18/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 1/12/2026 | Approved | JON MCHUGH |
| Final | 1/12/2026 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 1/12/2026 | Approved | JON MCHUGH |
| HVAC-Final | 1/12/2026 | Approved | JON MCHUGH |
| PLUMBING-Final | 1/12/2026 | Approved | JON MCHUGH |