5615 N TROOST AVE 91601
Certificate Information: 5615 N TROOST AVE 91601
- Application / Permit
- 25014-20000-00579
- Plan Check / Job No.
- B25VN03288
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(b)(1)3 WITH IRREGULAR SHAPED 42'-3" X 36' ADDITION & ENTIRELY ALL NEW ROOF FRAMING. ALL WORK PER ENGINEERING. SEE COMMENTS.
- Permit Issued
- Issued on 2/27/2025
- Issuing Office
- Current Status
- CofO in Progress on 4/29/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 2/19/2025 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 2/20/2025 | APPLICANT |
| Applicant returned to address corrections | 2/25/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 2/27/2025 | HAYATO TSUCHIYA |
| Issued | 2/27/2025 | APPLICANT |
| CofO in Progress | 4/29/2026 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 2/20/2025 | WALTER RAMIREZ |
| Construction within easement | Cleared | 2/20/2025 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 2/20/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 2/21/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 | 17770 CAPE JASMINE RD CANYON COUNTRY, CA 91387 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/4/2025 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 4/4/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/21/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/29/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/11/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 6/11/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 6/11/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 6/11/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 6/11/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/27/2025 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/27/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/27/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/27/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/2/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/2/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/2/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 7/15/2025 | Corrections Issued | JAVIER RAMOS JR |
| Shower Pan | 7/15/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 7/18/2025 | Approved | JAVIER RAMOS JR |
| Sewer | 7/18/2025 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/23/2025 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 7/23/2025 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 7/23/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Underground Mechanical | 7/23/2025 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 8/1/2025 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 8/1/2025 | Approved | JAVIER RAMOS JR |
| Sewer | 8/1/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 10/16/2025 | Corrections Issued | RYAN SALAZAR |
| Final | 10/16/2025 | Corrections Issued | RYAN SALAZAR |
| Service/Power Release | 10/16/2025 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/22/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 10/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 10/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 10/22/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 10/22/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 10/22/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 10/22/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 10/22/2025 | SGSOV Not Required | JAVIER RAMOS JR |
| Smoke Detectors | 10/22/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/1/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/1/2026 | Corrections Issued | JAVIER RAMOS JR |
| Service/Power Release | 4/1/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/29/2026 | OK to Issue CofO | JAVIER RAMOS JR |