7023-7025 N COMANCHE AVE 91306
Certificate Information: 7023-7025 N COMANCHE AVE 91306
- Application / Permit
- 25014-20000-00577
- Plan Check / Job No.
- B25VN03273
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 18'-7" X 20'-4" ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GC 66323(a)(1) AND 66333.
- Permit Issued
- Issued on 4/28/2025
- Issuing Office
- Current Status
- CofO Issued on 9/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | RAPHAEL ROSAS |
| Corrections Issued | 2/25/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 2/26/2025 | STEVEN KIM |
| Building Plans Picked Up | 2/27/2025 | APPLICANT |
| Applicant returned to address corrections | 3/27/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 4/28/2025 | RAPHAEL ROSAS |
| Issued | 4/28/2025 | APPLICANT |
| CofO in Progress | 8/13/2025 | ALEXANDER HANDY |
| Permit Finaled | 9/26/2025 | JOHN JANSON |
| CofO Issued | 9/26/2025 | JOHN JANSON |
| Permit Finaled | 9/26/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 3/1/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 3/3/2025 | SAFA JAVANMARDI |
| Senate Bill 9 | Cleared | 3/20/2025 | DAVID URITA |
| ZI | Cleared | 3/20/2025 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/6/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 5/6/2025 | Partial Approval | ALEXANDER HANDY |
| Sewer | 5/6/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 5/9/2025 | Conditional Approval | ROBERT GOLD |
| Sewer | 5/12/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Special/Order Compliance | 5/12/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 5/14/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 5/14/2025 | Partial Approval | ALEXANDER HANDY |
| Sewer | 5/14/2025 | Approved | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 5/19/2025 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 6/11/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 6/11/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 6/11/2025 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 6/11/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 6/11/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 6/11/2025 | Approved | ALEXANDER HANDY |
| Insulation | 6/18/2025 | Conditional Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 6/18/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 6/23/2025 | Partial Approval | SCOTT SOBEL |
| Drywall Nailing | 6/26/2025 | Approved | SCOTT SOBEL |
| ELECTRICAL-Final | 8/12/2025 | Approved | ALEXANDER HANDY |
| Final | 8/12/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 8/12/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 8/12/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 8/12/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 8/12/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 8/12/2025 | Approved | ALEXANDER HANDY |