4146 N HIGH VALLEY ROAD 91436
Certificate Information: 4146 N HIGH VALLEY ROAD 91436
- Application / Permit
- 25014-20000-00561
- Plan Check / Job No.
- B25VN03211
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL, CONVERT PORTION OF GARAGE TO SFD, & 21'3"X30'4" 2ND FLOOR ADDITION. (NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT)
- Permit Issued
- Issued on 5/30/2025
- Issuing Office
- Valley
- Current Status
- Issued on 5/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | MARVEL DELACRUZ |
| Corrections Issued | 2/15/2025 | MARVEL DELACRUZ |
| Quality Review Completed | 2/25/2025 | RARES BODEA |
| Building Plans Picked Up | 2/26/2025 | APPLICANT |
| Applicant returned to address corrections | 4/15/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 5/23/2025 | MARVEL DELACRUZ |
| Plan Check Approved | 5/30/2025 | MARVEL DELACRUZ |
| Issued | 5/30/2025 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/5/2025 | ASHLEY RODARTE |
| BHO/Hillside ordinance | Cleared | 3/6/2025 | RYAN CASTRO |
| BHO/Hillside ordinance | Cleared | 3/6/2025 | RYAN CASTRO |
| BHO/Hillside ordinance | Cleared | 3/6/2025 | RYAN CASTRO |
| BHO/Hillside ordinance | Cleared | 3/6/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 3/7/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 3/7/2025 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 3/14/2025 | GERMAN RODRIGUEZ MENDOZA |
| Distance to fire station | Cleared | 4/4/2025 | LAVEON RIDER |
| Hydrant and Access approval | Cleared | 4/4/2025 | LAVEON RIDER |
| BHO/Hillside ordinance | Cleared | 5/16/2025 | RYAN CASTRO |
| GPI Written Notices | Cleared | 5/30/2025 | MARVEL DELACRUZ |
Contact Information
| Contractor | Trig Builders Inc; Lic. No.: 1030887-B | 6442 COLDWATER CANYON AVE 111 NORTH HOLLYWOOD, CA 91606 |
| Engineer | Nirattisai,, Preston; Lic. No.: C85115 | 28411 ASCENT WAY SANTA CLARITA, CA 91350 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/9/2025 | Conditional Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 6/9/2025 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/12/2025 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 7/9/2025 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/14/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 7/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 7/17/2025 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 7/17/2025 | Approved | THOMAS FINNILA |
| Deputy Wood Construction | 7/22/2025 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 7/22/2025 | Corrections Issued | THOMAS FINNILA |
| Deputy Wood Construction | 7/28/2025 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 7/28/2025 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2025 | Partial Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 7/31/2025 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 7/31/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 7/31/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 7/31/2025 | Corrections Issued | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 7/31/2025 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/7/2025 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 8/7/2025 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/13/2025 | Approved | MORRIS JACKSON |
| Green Building Rough | 8/13/2025 | Approved | MORRIS JACKSON |
| Insulation | 8/13/2025 | Approved | MORRIS JACKSON |
| Special/Order Compliance | 8/13/2025 | Corrections Issued | MORRIS JACKSON |
| Drywall Nailing | 8/19/2025 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/19/2025 | Approved | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/13/2026 | Approved | THOMAS FINNILA |
| Smoke Detectors | 7/13/2026 | Corrections Issued | THOMAS FINNILA |