17022 W MCKEEVER ST 91344
Certificate Information: 17022 W MCKEEVER ST 91344
- Application / Permit
- 25014-20000-00546
- Plan Check / Job No.
- B25VN03113
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan CONVERT PORTION OF GARAGE TO 2 STORY ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 5/30/2025
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | JESSE VIDUYA |
| Corrections Issued | 3/10/2025 | JESSE VIDUYA |
| Quality Review Completed | 3/13/2025 | CHAD DOI |
| Applicant returned to address corrections | 5/9/2025 | JESSE VIDUYA |
| Applicant returned to address corrections | 5/19/2025 | JESSE VIDUYA |
| Plan Check Approved | 5/29/2025 | JESSE VIDUYA |
| Issued | 5/30/2025 | APPLICANT |
| CofO in Progress | 2/24/2026 | STEVEN BACK |
| Permit Finaled | 3/12/2026 | JOHN JANSON |
| CofO Issued | 3/12/2026 | JOHN JANSON |
| Permit Finaled | 3/12/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/18/2025 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 4/4/2025 | GERMAN RODRIGUEZ MENDOZA |
| Roof/Waste drainage to street | Cleared | 4/9/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 4/23/2025 | GEVORK KARAPETYAN |
| GPI Written Notices | Cleared | 5/9/2025 | JESSE VIDUYA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 6/23/2025 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 6/23/2025 | Not Ready for Inspection | STEVEN BACK |
| Pre-Inspection | 6/23/2025 | Partial Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 6/27/2025 | Not Ready for Inspection | STEVEN BACK |
| Footing/Foundation/Slab | 6/27/2025 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 6/27/2025 | Partial Approval | STEVEN BACK |
| Deputy Reinf. Concrete | 7/2/2025 | Approved | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 7/2/2025 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 7/2/2025 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 7/2/2025 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 7/22/2025 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2025 | Partial Approval | JEFFREY PARD |
| Deputy Wood Construction | 10/17/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 10/17/2025 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 10/31/2025 | Not Ready for Inspection | STEVEN BACK |
| Deputy Drilled-In Anchors | 10/31/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Approved | STEVEN BACK |
| Green Building Rough | 10/31/2025 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 10/31/2025 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 11/4/2025 | Approved | STEVEN BACK |
| HVAC-Rough | 11/4/2025 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 11/4/2025 | Not Ready for Inspection | STEVEN BACK |
| Shower Pan | 11/4/2025 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 11/10/2025 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 11/10/2025 | Approved | STEVEN BACK |
| HVAC-Rough | 11/10/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 11/10/2025 | Not Ready for Inspection | STEVEN BACK |
| Shower Pan | 11/10/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 11/14/2025 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 11/18/2025 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 11/20/2025 | Approved | STEVEN BACK |
| Insulation | 11/20/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 12/1/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/4/2025 | Approved | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 2/6/2026 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 2/6/2026 | Not Ready for Inspection | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 2/6/2026 | SGSOV Not Ready | JEFFREY PARD |
| Smoke Detectors | 2/6/2026 | Not Ready for Inspection | JEFFREY PARD |
| Final | 2/18/2026 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 2/18/2026 | Approved | STEVEN BACK |
| Green Building Final | 2/18/2026 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 2/18/2026 | Approved | STEVEN BACK |
| Final | 2/24/2026 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 2/24/2026 | Approved | STEVEN BACK |