24036 W ARMINTA ST 91304

Certificate Information: 24036 W ARMINTA ST 91304

Application / Permit
25014-20000-00533
Plan Check / Job No.
B25VN02989
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan New attached covered patio.
Permit Issued
Issued on 4/2/2025
Issuing Office
Current Status
CofO Issued on 4/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2025 APPLICANT
Assigned to Plan Check Engineer 2/21/2025 DANIEL SANJUAN
Corrections Issued 2/22/2025 DANIEL SANJUAN
Plan Check Approved 3/18/2025 JOHN MESIAS
Issued 4/2/2025 APPLICANT
CofO in Progress 9/26/2025 CHRIS CHRISTENSEN
Permit Finaled 4/4/2026 MICHAEL PELHAM
CofO Issued 4/4/2026 MICHAEL PELHAM
Permit Finaled 4/4/2026 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/14/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 3/14/2025 RYAN CASTRO

Contact Information

Contractor Century Development Corporation; Lic. No.: 297227-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/9/2025 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/9/2025 Conditional Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 6/10/2025 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 6/12/2025 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/3/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/3/2025 Conditional Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/3/2025 Approved CHRIS CHRISTENSEN
Wood Frame 7/3/2025 Approved CHRIS CHRISTENSEN
Drywall Nailing 7/31/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 7/31/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Final 9/19/2025 Approved CHRIS CHRISTENSEN
Final 9/19/2025 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/19/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/19/2025 SGSOV Not Ready CHRIS CHRISTENSEN
Final 9/25/2025 OK to Issue CofO CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 9/25/2025 Approved CHRIS CHRISTENSEN