8921 N SWINTON AVE 91343

Certificate Information: 8921 N SWINTON AVE 91343

Application / Permit
25014-20000-00528
Plan Check / Job No.
B25VN02962
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND 2-STORY 18'-6" x 34'-6" ADDITION TO (E) SFD PER ENGINEERING
Permit Issued
Issued on 5/20/2025
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 ALFRED RAMIREZ
Corrections Issued 2/8/2025 ALFRED RAMIREZ
Quality Review Completed 2/11/2025 STEVEN KIM
Building Plans Picked Up 2/12/2025 APPLICANT
Plan Check Approved 5/20/2025 ALFRED RAMIREZ
Issued 5/20/2025 APPLICANT
CofO in Progress 2/18/2026 GAREN HAYRAPETYAN
No Progress 2/28/2026 JOSE AVILA
CofO in Progress 2/28/2026 JOSE AVILA
CofO in Progress 3/3/2026 JOSE AVILA
CofO in Progress 5/4/2026 JOSE AVILA
Permit Finaled 5/14/2026 RUBEN SALAS
CofO Issued 5/14/2026 RUBEN SALAS
Permit Finaled 5/14/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/17/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/18/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/29/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 7/3/2025 Partial Approval SALVADOR MARTINEZ
Deputy Drilled-In Anchors 7/8/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/14/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 8/1/2025 Not Ready for Inspection GAREN HAYRAPETYAN
BUILDING-Rough-Frame 8/8/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 8/8/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 8/8/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 8/8/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/8/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 8/8/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/11/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Shower Pan 8/11/2025 Approved GAREN HAYRAPETYAN
Insulation 8/15/2025 Corrections Issued RYAN SALAZAR
Drywall Nailing 8/20/2025 Not Ready for Inspection SALVADOR MARTINEZ
Drywall Nailing 8/25/2025 Approved JAVIER RAMOS JR
Insulation 8/25/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/4/2026 Approved GAREN HAYRAPETYAN
Final 2/4/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 2/4/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 2/4/2026 Approved GAREN HAYRAPETYAN
Final 2/18/2026 OK to Issue CofO GAREN HAYRAPETYAN
Special/Order Compliance 3/4/2026 Corrections Issued GAREN HAYRAPETYAN
Final 5/1/2026 Not Ready for Inspection JOSE AVILA