10018 N AQUEDUCT AVE 91343

Certificate Information: 10018 N AQUEDUCT AVE 91343

Application / Permit
25014-20000-00516
Plan Check / Job No.
B25VN02853
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'-6" X 15'-0" IRREGULAR SHAPED ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1). PER ENGINEER DESIGN.
Permit Issued
Issued on 2/20/2025
Issuing Office
Current Status
CofO Issued on 2/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2025 APPLICANT
Assigned to Plan Check Engineer 2/12/2025 ARTIN ZARUKIAN
Corrections Issued 2/15/2025 ARTIN ZARUKIAN
Building Plans Picked Up 2/18/2025 APPLICANT
Issued 2/20/2025 APPLICANT
CofO in Progress 1/23/2026 CHRISTOPHER ROJAS
Permit Finaled 2/3/2026 RUBEN SALAS
CofO Issued 2/3/2026 RUBEN SALAS
Permit Finaled 2/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/18/2025 LEE GUILBEAUX
Construction near power lines Cleared 2/18/2025 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/18/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/18/2025 LEE GUILBEAUX
Sewer availability Cleared 2/18/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/18/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/12/2025 Corrections Issued JAVIER RAMOS JR
Sewer 3/12/2025 Approved JAVIER RAMOS JR
Underground Mechanical 3/12/2025 Partial Approval JAVIER RAMOS JR
Deputy Wood Construction 3/24/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/27/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 3/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 3/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 3/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Deputy Wood Construction 4/1/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 4/28/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 4/28/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 4/28/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/30/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/30/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 4/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 4/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 4/30/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/7/2025 Approved KEVIN BERBERYAN
HVAC-Rough 5/7/2025 Corrections Issued KEVIN BERBERYAN
Insulation 5/19/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 5/19/2025 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 6/2/2025 Approved LOUIS ESCOTO
Green Building Rough 6/2/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 6/2/2025 Approved LOUIS ESCOTO
Final 12/26/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 12/26/2025 Approved KEVIN BERBERYAN
Green Building Final 12/26/2025 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Final 12/26/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/26/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 12/26/2025 Approved KEVIN BERBERYAN
Final 1/15/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 1/15/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 1/22/2026 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 1/22/2026 Approved CHRISTOPHER ROJAS
Service/Power Release 1/22/2026 Approved CHRISTOPHER ROJAS