6148-6150 N LEDERER AVE 91367

Certificate Information: 6148-6150 N LEDERER AVE 91367

Application / Permit
25014-20000-00488
Plan Check / Job No.
B25VN02773
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: Addition of 2nd story Accessory Dwelling Unit above (E) one-story single family dwelling per LAMC 12.22 A.33 (c) and remodel (E) attached carport
Permit Issued
Issued on 5/9/2025
Issuing Office
Current Status
CofO Issued on 4/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2025 APPLICANT
Assigned to Plan Check Engineer 2/27/2025 ALEXANDER JOO
Corrections Issued 3/3/2025 ALEXANDER JOO
Quality Review Completed 3/3/2025 GARO TELMI
Applicant returned to address corrections 4/22/2025 ALEXANDER JOO
Plan Check Approved 5/1/2025 ALEXANDER JOO
Issued 5/9/2025 APPLICANT
CofO in Progress 3/13/2026 GEVORK IPCHYAN
Permit Finaled 4/11/2026 MICHAEL PELHAM
CofO Issued 4/11/2026 MICHAEL PELHAM
Permit Finaled 4/11/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 3/4/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 3/4/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 3/9/2025 SAFA JAVANMARDI
Sewer availability Cleared 3/9/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/11/2025 Conditional Approval TROY SANDERS
Footing/Foundation/Slab 8/13/2025 Partial Approval TROY SANDERS
PLUMBING-Rough 8/13/2025 Partial Approval TROY SANDERS
Deputy Drilled-In Anchors 8/18/2025 Conditional Approval HENRY KIM
Footing/Foundation/Slab 8/25/2025 Approved GEVORK IPCHYAN
Deputy Other (see comments) 8/26/2025 Conditional Approval ROBERT GOLD
Deputy Reinf. Concrete 8/26/2025 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Partial Approval GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Corrections Issued GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/24/2025 Partial Approval GEVORK IPCHYAN
Insulation 10/24/2025 Partial Approval GEVORK IPCHYAN
Deputy Wood Construction 10/30/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 11/3/2025 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 11/3/2025 Approved GEVORK IPCHYAN
Green Building Rough 11/3/2025 Partial Approval GEVORK IPCHYAN
HVAC-Rough 11/3/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 11/3/2025 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 11/3/2025 Approved GEVORK IPCHYAN
Insulation 11/14/2025 Conditional Approval GEVORK IPCHYAN
Drywall Nailing 11/19/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 12/3/2025 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 3/9/2026 Approved GEVORK IPCHYAN
ELECTRICAL-Final 3/9/2026 Approved GEVORK IPCHYAN
Final 3/9/2026 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 3/9/2026 Partial Approval GEVORK IPCHYAN
Green Building Rough 3/9/2026 Approved GEVORK IPCHYAN
HVAC-Final 3/9/2026 Partial Approval GEVORK IPCHYAN
PLUMBING-Final 3/9/2026 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 3/9/2026 Approved GEVORK IPCHYAN
Final 3/12/2026 OK to Issue CofO GEVORK IPCHYAN
Green Building Final 3/12/2026 Approved GEVORK IPCHYAN
HVAC-Final 3/12/2026 Approved GEVORK IPCHYAN
Service/Power Release 3/13/2026 Approved GEVORK IPCHYAN