2909-2909 1/2 W 43RD PL 90008
Certificate Information: 2909-2909 1/2 W 43RD PL 90008
- Application / Permit
- 25014-20000-00478
- Plan Check / Job No.
- B25VN02725
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 2ND FLOOR AND CONVERT EXISTING SIX CAR GARAGE INTO (2) ACCESSORY DWELLING UNITS AS PER GC 66323(a)(4), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/2/2025
- Issuing Office
- Metro
- Current Status
- Issued on 5/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2025 | RARES BODEA |
| Corrections Issued | 2/11/2025 | RARES BODEA |
| Quality Review Completed | 2/13/2025 | STEVEN KIM |
| Building Plans Picked Up | 2/18/2025 | APPLICANT |
| Plan Check Approved | 4/28/2025 | RARES BODEA |
| Issued | 5/2/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/25/2025 | RIDWAN HARDY |
| Address approval | Cleared | 4/2/2025 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2025 | JEREMY CHOK |
| Roof/Waste drainage to street | Cleared | 4/2/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 4/2/2025 | JEREMY CHOK |
Contact Information
| Architect | Nigosian,, Michael Nickolas; Lic. No.: C35308 | 75-572 PAINTED DESERT DRIVE INDIAN WELLS, CA 92210 |
| Contractor | Owner-Builder | , |
| Engineer | Boranian,, Paul; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/17/2025 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 9/23/2025 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 10/10/2025 | Not Ready for Inspection | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 2/25/2026 | Not Ready for Inspection | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 2/25/2026 | Not Ready for Inspection | WILLIAM MICHALAK |
| Pre-Inspection | 3/4/2026 | Corrections Issued | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 3/5/2026 | Approved | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 3/5/2026 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 3/6/2026 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 5/29/2026 | Corrections Issued | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 5/29/2026 | Corrections Issued | WILLIAM MICHALAK |
| Green Building Rough | 5/29/2026 | Not Ready for Inspection | WILLIAM MICHALAK |
| HVAC-Rough | 5/29/2026 | Corrections Issued | WILLIAM MICHALAK |
| PLUMBING-Rough | 5/29/2026 | Corrections Issued | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 6/4/2026 | Corrections Issued | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 6/4/2026 | Partial Approval | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2026 | Partial Approval | WILLIAM MICHALAK |
| Green Building Rough | 6/4/2026 | Not Ready for Inspection | WILLIAM MICHALAK |
| HVAC-Rough | 6/4/2026 | Partial Approval | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 6/4/2026 | Partial Approval | WILLIAM MICHALAK |
| PLUMBING-Rough | 6/4/2026 | Partial Approval | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 6/11/2026 | Approved | WILLIAM MICHALAK |
| PLUMBING-Rough | 6/15/2026 | Partial Approval | WILLIAM MICHALAK |
| HVAC-Rough | 6/23/2026 | Approved | WILLIAM MICHALAK |
| Insulation | 6/23/2026 | Corrections Issued | WILLIAM MICHALAK |
| Pre-Inspection | 6/23/2026 | Approved | WILLIAM MICHALAK |