19402 W PARTHENIA ST 91324

Certificate Information: 19402 W PARTHENIA ST 91324

Application / Permit
25014-20000-00434
Plan Check / Job No.
B25VN02492
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: DETACHED GARAGE CONVERSION AND ADDITION TO ADU PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
Permit Issued
Issued on 5/13/2025
Issuing Office
Current Status
CofO Issued on 6/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2025 APPLICANT
Assigned to Plan Check Engineer 2/25/2025 RICARDO RAMIREZ
Corrections Issued 2/26/2025 RICARDO RAMIREZ
Applicant returned to address corrections 4/24/2025 SUNMIN LEE
Applicant returned to address corrections 4/28/2025 SUNMIN LEE
Plan Check Approved 4/29/2025 FERNANDO FLORES
Issued 5/13/2025 APPLICANT
CofO in Progress 6/8/2026 JEFFREY HARTLINE
Permit Finaled 6/17/2026 JOHN JANSON
Permit Finaled 6/17/2026 JOHN JANSON
CofO Issued 6/17/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/3/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/3/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/3/2025 CARLOS AGUILERA
Sewer availability Cleared 3/19/2025 CARLOS AGUILERA
Construction near power lines Cleared 4/11/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/24/2025 Approved CHRIS CHRISTENSEN
Underground Mechanical 8/13/2025 Approved JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 9/9/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 11/13/2025 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Partial Approval JEFFREY HARTLINE
HVAC-Rough 11/13/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 11/13/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 11/14/2025 Approved JEFFREY HARTLINE
HVAC-Rough 11/14/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 11/14/2025 Approved JEFFREY HARTLINE
Wood Frame 11/14/2025 Not Ready for Inspection JEFFREY HARTLINE
Interior/Exterior Lathing 11/21/2025 Partial Approval JEFFREY HARTLINE
Shower Pan 11/21/2025 Not Ready for Inspection JEFFREY HARTLINE
Shower Pan 11/26/2025 Approved JEFFREY HARTLINE
Wood Frame 12/5/2025 Conditional Approval CHRIS CHRISTENSEN
Insulation 12/15/2025 Not Ready for Inspection KRISTEN CAUSEY
Drywall Nailing 12/29/2025 Approved JEFFREY HARTLINE
Underground Mechanical 1/26/2026 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 4/1/2026 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 5/1/2026 Approved CHRIS CHRISTENSEN
Final 5/1/2026 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/1/2026 Approved CHRIS CHRISTENSEN
Green Building Final 5/1/2026 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 5/1/2026 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/1/2026 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 5/1/2026 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 5/18/2026 Approved CHRIS CHRISTENSEN
Final 5/18/2026 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 5/18/2026 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 5/18/2026 Approved CHRIS CHRISTENSEN
PLUMBING-Final 5/18/2026 Approved CHRIS CHRISTENSEN
Smoke Detectors 5/18/2026 Approved CHRIS CHRISTENSEN
Final 6/5/2026 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 6/5/2026 Approved JEFFREY HARTLINE