7442 N BALCOM AVE 91335

Certificate Information: 7442 N BALCOM AVE 91335

Application / Permit
25014-20000-00431
Plan Check / Job No.
B25VN02472
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT GARAGE TO BEDROOM AND BATHROOM. ADD CARPORT AND ADDITION TO SFD FOR NEW PANTRY AND LAUNDRY ROOM.
Permit Issued
Issued on 2/18/2025
Issuing Office
Valley
Current Status
CofO Issued on 10/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 JEROME MAGAT PALMA
Corrections Issued 2/8/2025 JEROME MAGAT PALMA
Building Plans Picked Up 2/10/2025 APPLICANT
Plan Check Approved 2/13/2025 YAQUB MIRZA
Issued 2/18/2025 APPLICANT
CofO in Progress 10/2/2025 ARUTYUN MADATYAN
Permit Finaled 10/20/2025 JOHN JANSON
CofO Issued 10/20/2025 JOHN JANSON
Permit Finaled 10/20/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/11/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 2/11/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/30/2025 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 6/3/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 6/3/2025 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 6/17/2025 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 6/17/2025 Partial Approval ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 6/20/2025 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 6/20/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/10/2025 Not Ready for Inspection JUAN ALVARADO
Green Building Rough 7/10/2025 Not Ready for Inspection JUAN ALVARADO
ELECTRICAL-Rough 7/14/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 7/14/2025 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 7/14/2025 Corrections Issued ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/16/2025 Partial Approval ARUTYUN MADATYAN
Green Building Rough 7/16/2025 Approved ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 7/16/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/21/2025 Approved KRISTEN CAUSEY
Drywall Nailing 7/21/2025 Approved KRISTEN CAUSEY
Insulation 7/21/2025 Approved KRISTEN CAUSEY
Final 9/22/2025 No Access for Inspection ROBERT GOLD
Green Building Final 9/22/2025 No Access for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV Not Ready ROBERT GOLD
Smoke Detectors 9/22/2025 No Access for Inspection ROBERT GOLD
ELECTRICAL-Final 10/1/2025 Approved ARUTYUN MADATYAN
Final 10/1/2025 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 10/1/2025 Approved ARUTYUN MADATYAN
HVAC-Final 10/1/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 10/1/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/1/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 10/1/2025 Approved ARUTYUN MADATYAN