8206 S BELFORD AVE 90045

Certificate Information: 8206 S BELFORD AVE 90045

Application / Permit
25014-20000-00423
Plan Check / Job No.
B25VN02424
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 8'6"X23'2" ADDN TO EXPAND EX LIVING & DINING ROOMS WITH NEW BATHROOM. CONSTRUCTION DESIGN PER ENGR.
Permit Issued
Issued on 2/25/2025
Issuing Office
Valley
Current Status
CofO Issued on 8/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 HAYATO TSUCHIYA
Corrections Issued 2/6/2025 HAYATO TSUCHIYA
Building Plans Picked Up 2/7/2025 APPLICANT
Plan Check Approved 2/25/2025 YAQUB MIRZA
Issued 2/25/2025 APPLICANT
CofO in Progress 7/31/2025 JESUS PINEDA
Permit Finaled 8/4/2025 RICHARD STEINBACH
CofO Issued 8/4/2025 RICHARD STEINBACH
Permit Finaled 8/4/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/10/2025 DIANA RENTERIA
Sewer availability Cleared 2/10/2025 DIANA RENTERIA
Grading Pre-Inspection Cleared 2/13/2025 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 2/18/2025 LIAM ODONOVAN

Contact Information

Contractor Concierge Home Remodeling; Lic. No.: 1071929-B 19562 VENTURA BLVD STE 226      TARZANA, CA 91356
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/9/2025 Approved JESUS PINEDA
PLUMBING-Rough 4/18/2025 Partial Approval TEMISTOCLES CAAL
Special/Order Compliance 4/18/2025 Partial Inspection JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Partial Approval BOBBY KEY
ELECTRICAL-Rough 5/9/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 5/21/2025 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 5/21/2025 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 5/21/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 5/27/2025 Not Ready for Inspection JESUS PINEDA
Interior/Exterior Lathing 5/27/2025 Not Ready for Inspection JESUS PINEDA
PLUMBING-Rough 5/27/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 5/28/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 5/28/2025 Partial Approval JESUS PINEDA
PLUMBING-Rough 5/28/2025 Approved JESUS PINEDA
Insulation 6/2/2025 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 6/6/2025 Approved JESUS PINEDA
Drywall Nailing 6/6/2025 Corrections Issued JESUS PINEDA
Green Building Rough 6/6/2025 Approved JESUS PINEDA
HVAC-Rough 6/6/2025 Approved JESUS PINEDA
Insulation 6/6/2025 Approved JESUS PINEDA
Shower Pan 6/6/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 6/17/2025 Approved TEMISTOCLES CAAL
Drywall Nailing 6/26/2025 Approved JAYLIN GRAVITTE
Special/Order Compliance 6/26/2025 Partial Inspection HERBERT GIRON
Special/Order Compliance 6/26/2025 Partial Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 7/25/2025 Approved BOBBY KEY
Final 7/25/2025 Corrections Issued BOBBY KEY
Green Building Final 7/25/2025 Approved BOBBY KEY
HVAC-Final 7/25/2025 Corrections Issued BOBBY KEY
PLUMBING-Final 7/25/2025 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Not Ready BOBBY KEY
Service/Power Release 7/25/2025 Approved BOBBY KEY
Smoke Detectors 7/25/2025 Approved BOBBY KEY
Final 7/30/2025 OK to Issue CofO JESUS PINEDA
HVAC-Final 7/30/2025 Approved JESUS PINEDA
PLUMBING-Final 7/30/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Approved JESUS PINEDA