8206 S BELFORD AVE 90045
Certificate Information: 8206 S BELFORD AVE 90045
- Application / Permit
- 25014-20000-00423
- Plan Check / Job No.
- B25VN02424
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 8'6"X23'2" ADDN TO EXPAND EX LIVING & DINING ROOMS WITH NEW BATHROOM. CONSTRUCTION DESIGN PER ENGR.
- Permit Issued
- Issued on 2/25/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2025 | HAYATO TSUCHIYA |
| Corrections Issued | 2/6/2025 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 2/7/2025 | APPLICANT |
| Plan Check Approved | 2/25/2025 | YAQUB MIRZA |
| Issued | 2/25/2025 | APPLICANT |
| CofO in Progress | 7/31/2025 | JESUS PINEDA |
| Permit Finaled | 8/4/2025 | RICHARD STEINBACH |
| CofO Issued | 8/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/10/2025 | DIANA RENTERIA |
| Sewer availability | Cleared | 2/10/2025 | DIANA RENTERIA |
| Grading Pre-Inspection | Cleared | 2/13/2025 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2025 | LIAM ODONOVAN |
Contact Information
| Contractor | Concierge Home Remodeling; Lic. No.: 1071929-B | 19562 VENTURA BLVD STE 226 TARZANA, CA 91356 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/9/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 4/18/2025 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 4/18/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 5/9/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 5/21/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 5/21/2025 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 5/21/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 5/27/2025 | Not Ready for Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 5/27/2025 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 5/27/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 5/28/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/28/2025 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 5/28/2025 | Approved | JESUS PINEDA |
| Insulation | 6/2/2025 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 6/6/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 6/6/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 6/6/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 6/6/2025 | Approved | JESUS PINEDA |
| Insulation | 6/6/2025 | Approved | JESUS PINEDA |
| Shower Pan | 6/6/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/17/2025 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 6/26/2025 | Approved | JAYLIN GRAVITTE |
| Special/Order Compliance | 6/26/2025 | Partial Inspection | HERBERT GIRON |
| Special/Order Compliance | 6/26/2025 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 7/25/2025 | Approved | BOBBY KEY |
| Final | 7/25/2025 | Corrections Issued | BOBBY KEY |
| Green Building Final | 7/25/2025 | Approved | BOBBY KEY |
| HVAC-Final | 7/25/2025 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 7/25/2025 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Not Ready | BOBBY KEY |
| Service/Power Release | 7/25/2025 | Approved | BOBBY KEY |
| Smoke Detectors | 7/25/2025 | Approved | BOBBY KEY |
| Final | 7/30/2025 | OK to Issue CofO | JESUS PINEDA |
| HVAC-Final | 7/30/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 7/30/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Approved | JESUS PINEDA |