9674 N SANDUSKY AVE 91331

Certificate Information: 9674 N SANDUSKY AVE 91331

Application / Permit
25014-20000-00416
Plan Check / Job No.
B25VN02393
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION ( 10'-6" x12'2", 142.08 S.F.) TO EXISTING ONE STORY SINGLE FAMILY HOME.
Permit Issued
Issued on 2/20/2025
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2025 APPLICANT
Assigned to Plan Check Engineer 2/4/2025 TSE MING HUANG
Corrections Issued 2/5/2025 TSE MING HUANG
Plan Check Approved 2/19/2025 TSE MING HUANG
Issued 2/20/2025 APPLICANT
CofO in Progress 5/9/2025 MICHEL ABAJAN
Permit Finaled 5/15/2025 RUBEN SALAS
CofO Issued 5/15/2025 RUBEN SALAS
Permit Finaled 5/15/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/6/2025 LEE GUILBEAUX
Sewer availability Cleared 2/6/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/6/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/7/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Barragan,, Pedro; Lic. No.: C90531 329 N HUBBARD AVE      SAN FERNANDO, CA 91340

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/21/2025 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 3/25/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 3/26/2025 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 4/10/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/10/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 4/10/2025 Approved MICHEL ABAJAN
Insulation 4/18/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/18/2025 Approved MICHEL ABAJAN
Drywall Nailing 4/21/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/8/2025 Approved MICHEL ABAJAN
Final 5/8/2025 OK to Issue CofO MICHEL ABAJAN
Footing/Foundation/Slab 5/8/2025 Approved MICHEL ABAJAN
HVAC-Final 5/8/2025 Approved MICHEL ABAJAN
PLUMBING-Final 5/8/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 5/8/2025 Approved MICHEL ABAJAN