9674 N SANDUSKY AVE 91331
Certificate Information: 9674 N SANDUSKY AVE 91331
- Application / Permit
- 25014-20000-00416
- Plan Check / Job No.
- B25VN02393
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION ( 10'-6" x12'2", 142.08 S.F.) TO EXISTING ONE STORY SINGLE FAMILY HOME.
- Permit Issued
- Issued on 2/20/2025
- Issuing Office
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2025 | TSE MING HUANG |
| Corrections Issued | 2/5/2025 | TSE MING HUANG |
| Plan Check Approved | 2/19/2025 | TSE MING HUANG |
| Issued | 2/20/2025 | APPLICANT |
| CofO in Progress | 5/9/2025 | MICHEL ABAJAN |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
| CofO Issued | 5/15/2025 | RUBEN SALAS |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/6/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/6/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/6/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barragan,, Pedro; Lic. No.: C90531 | 329 N HUBBARD AVE SAN FERNANDO, CA 91340 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/21/2025 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 3/25/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 3/26/2025 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/10/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/10/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 4/10/2025 | Approved | MICHEL ABAJAN |
| Insulation | 4/18/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/18/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/21/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/8/2025 | Approved | MICHEL ABAJAN |
| Final | 5/8/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/8/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 5/8/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/8/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 5/8/2025 | Approved | MICHEL ABAJAN |