3390 N VISTA HAVEN ROAD 91403
Certificate Information: 3390 N VISTA HAVEN ROAD 91403
- Application / Permit
- 25014-20000-00411
- Plan Check / Job No.
- B25VN02362
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EX. SFD. EXPAND MASTER BEDROOM AND BATHROOM. REMODEL KITCHEN AND EX. BATHROOM. CREATE NEW POWDER ROOM, CLOSET AND LAUDRY ROOM. WORK PER ENGINEER.
- Permit Issued
- Issued on 6/25/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 2/6/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 2/11/2025 | APPLICANT |
| Applicant returned to address corrections | 3/19/2025 | ROSENDO MEDINA |
| Plan Check Approved | 6/25/2025 | ROSENDO MEDINA |
| Issued | 6/25/2025 | APPLICANT |
| CofO in Progress | 3/12/2026 | MICHAEL CORTEZ |
| CofO Issued | 4/2/2026 | RUBEN SALAS |
| Permit Finaled | 4/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/13/2025 | ROBERT PINA |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/24/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/24/2025 | BIAINA HARITUNIAN |
| Miscellaneous | Cleared | 4/1/2025 | JASON CHAN |
| ZA Case | Cleared | 4/1/2025 | JASON CHAN |
| Specific Plan | Cleared | 6/18/2025 | JUDE HERNANDEZ |
Contact Information
| Contractor | Shahnazarian Edick; Lic. No.: 1068047-B | 415 EAST DRYDEN #105 GLENDALE, CA 91207 |
| Engineer | Minn,, Wenchung; Lic. No.: C42605 | 3358 W 157TH ST GARDENA, CA 90249 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/8/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2025 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 7/29/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/19/2025 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 8/19/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 8/19/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 9/8/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 9/8/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 9/8/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 9/8/2025 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/22/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 9/22/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 9/22/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 9/22/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 9/22/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 9/29/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 9/29/2025 | Approved | JACK KARGODORIAN |
| Insulation | 9/29/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 9/29/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 9/29/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 9/29/2025 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 1/13/2026 | Approved | MISAEL ESPARZA |
| Final | 3/4/2026 | Corrections Issued | MICHAEL CORTEZ |
| Final | 3/11/2026 | Partial Approval | MICHAEL CORTEZ |
| Green Building Final | 3/11/2026 | Approved | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Approved | MICHAEL CORTEZ |
| Smoke Detectors | 3/11/2026 | Approved | MICHAEL CORTEZ |
| Final | 3/12/2026 | OK to Issue CofO | MICHAEL CORTEZ |