10159 W STAGG ST 91352

Certificate Information: 10159 W STAGG ST 91352

Application / Permit
25014-20000-00394
Plan Check / Job No.
B25VN02257
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: REMODEL AND ADDITION TO (E) SFD AND ATTACH PATIO COVER
Permit Issued
Issued on 7/3/2025
Issuing Office
Current Status
Issued on 7/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/30/2025 APPLICANT
Assigned to Plan Check Engineer 2/4/2025 MOHAMMAD ESMAILI
Corrections Issued 2/4/2025 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/26/2025 MOHAMMAD ESMAILI
Plan Check Approved 3/4/2025 MOHAMMAD ESMAILI
Issued 7/3/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/14/2025 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 2/14/2025 EDGAR ALCARAZ

Contact Information

Architect Krunic,, Dina; Lic. No.: NA38613       ,
Contractor 360 Contractors Group Inc; Lic. No.: 1001481-B       ,
Engineer Aronianpour,, Eilan; Lic. No.: NA88101       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/25/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 8/6/2025 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 8/11/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Partial Approval DAVID ANDERSON
PLUMBING-Rough 9/2/2025 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Partial Approval DAVID ANDERSON
Insulation 9/8/2025 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Corrections Issued DAVID ANDERSON
Green Building Rough 10/23/2025 Not Ready for Inspection DAVID ANDERSON
MERV13>=Rough 10/23/2025 Not Ready for Inspection DAVID ANDERSON
Deputy Wood Construction 10/24/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/14/2025 Partial Approval DAVID ANDERSON
PLUMBING-Rough 1/21/2026 Approved DAVID ANDERSON
Service/Power Release 3/27/2026 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 4/13/2026 Approved DAVID ANDERSON
ELECTRICAL-Rough 4/13/2026 Approved DAVID ANDERSON
Green Building Rough 4/13/2026 Approved DAVID ANDERSON
HVAC-Rough 4/13/2026 Approved DAVID ANDERSON
MERV13>=Rough 4/13/2026 Approved DAVID ANDERSON
PLUMBING-Rough 4/13/2026 Approved DAVID ANDERSON
Insulation 4/28/2026 Corrections Issued DAVID ANDERSON
Shower Pan 4/28/2026 Approved DAVID ANDERSON
Drywall Nailing 5/11/2026 Approved DAVID ANDERSON
Insulation 5/11/2026 Approved DAVID ANDERSON