11445 W DELANO ST 91606

Certificate Information: 11445 W DELANO ST 91606

Application / Permit
25014-20000-00384
Plan Check / Job No.
B25VN02176
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
IRREG SHAPED ACCESSORY DWELLING UNIT ADDITION TO (E) DETACHED GARAGE PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 6/6/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2025 APPLICANT
Assigned to Plan Check Engineer 2/4/2025 JEROME MAGAT PALMA
Corrections Issued 2/5/2025 JEROME MAGAT PALMA
Building Plans Picked Up 2/6/2025 APPLICANT
Plan Check Approved 4/10/2025 KAMYAR EMAMI
Issued 6/6/2025 APPLICANT
CofO in Progress 2/17/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 3/2/2026 RUBEN SALAS
CofO Issued 3/2/2026 RUBEN SALAS
Permit Finaled 3/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/7/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 2/7/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 2/18/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/18/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 4/4/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/11/2025 Approved JOSE AVILA
PLUMBING-Rough 8/25/2025 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 8/28/2025 Approved JOSE AVILA
Footing/Foundation/Slab 8/28/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 10/30/2025 Approved JOSE AVILA
ELECTRICAL-Rough 10/30/2025 Approved JOSE AVILA
Green Building Rough 10/30/2025 Approved JOSE AVILA
HVAC-Rough 10/30/2025 Approved JOSE AVILA
Interior/Exterior Lathing 10/30/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 10/30/2025 Approved JOSE AVILA
Insulation 11/6/2025 Approved JOSE AVILA
Interior/Exterior Lathing 11/6/2025 Approved JOSE AVILA
Drywall Nailing 11/13/2025 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 11/13/2025 Not Ready for Inspection JOSE AVILA
Drywall Nailing 11/24/2025 Partial Inspection JOSE AVILA
Drywall Nailing 11/25/2025 Approved MICHAEL CORTEZ
Gas Test 1/2/2026 Partial Approval MISAEL ESPARZA
Sewer 1/2/2026 Approved MISAEL ESPARZA
Final 2/5/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 2/5/2026 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/5/2026 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 2/5/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 2/9/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/9/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 2/9/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 2/13/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/13/2026 Approved ROBERTO PALACIOS-LOPEZ