ePlan: REMODEL TO EXISTING GARAGE AND ADDITION OF 2-STORY (40'-6.5" X 28'-2.75" IRR SHAPE) 2 ACCESSORY DWELLING UNITS PER CA GOVT. CODE 66323(a)(4). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 7/29/2025
Issuing Office
Current Status
Issued on 7/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/21/2025 APPLICANT
Assigned to Plan Check Engineer 1/23/2025 VAHAN JIVALAGIAN
Corrections Issued 1/30/2025 VAHAN JIVALAGIAN
Quality Review Completed 1/30/2025 OMID HEDAYAT
Applicant returned to address corrections 2/10/2025 VAHAN JIVALAGIAN
Applicant returned to address corrections 5/30/2025 VAHAN JIVALAGIAN
Applicant returned to address corrections 6/24/2025 VAHAN JIVALAGIAN
Applicant returned to address corrections 7/2/2025 VAHAN JIVALAGIAN
Plan Check Approved 7/24/2025 VAHAN JIVALAGIAN
Issued 7/29/2025 APPLICANT

Permit Application Clearance Information

GPI Written Notices Cleared 1/29/2025 VAHAN JIVALAGIAN
Grading Pre-Inspection Cleared 1/29/2025 VAHAN JIVALAGIAN
Address approval Cleared 2/4/2025 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 2/4/2025 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/5/2025 CARLOS RAMIREZ
Sewer availability Cleared 2/5/2025 CARLOS RAMIREZ
ZA Case Cleared 2/12/2025 ASHLEY RODARTE
Hydrant and Access approval Cleared 7/24/2025 LAVEON RIDER

Contact Information

Contractor Owner-Builder       ,
Engineer Khanlou,, Amir; Lic. No.: C87550 2603 BASIL LN      LOS ANGELES, CA 90077

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2026 Partial Inspection ALEXANDER HANDY
PLUMBING-Rough 4/9/2026 Corrections Issued DAVID FASTIGGI
Underground Mechanical 4/9/2026 Corrections Issued DAVID FASTIGGI
Underground Mechanical 4/10/2026 Approved DAVID FASTIGGI
Deputy Reinf. Concrete 5/7/2026 Approved ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 5/7/2026 Approved ALEXANDER HANDY
Footing/Foundation/Slab 5/7/2026 Approved ALEXANDER HANDY
Deputy Wood Construction 5/21/2026 Conditional Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 5/22/2026 Partial Approval JUAN ALVARADO
Deputy Wood Construction 6/23/2026 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 6/23/2026 Partial Approval ALEXANDER HANDY