12114-12116 W INAVALE PL 90049

Certificate Information: 12114-12116 W INAVALE PL 90049

Application / Permit
25014-20000-00378
Plan Check / Job No.
B25VN02127
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO KEEP (E) 2'-0" FOOTING AND CREATE A (N) 2-STORY IRREGULAR SHAPED 67'-0" x 75'-6" WITH ATTACHED GARAGE, COVERED PATIO, BALCONY AND 1-STORY ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) and (e) PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 4/4/2025
Issuing Office
Current Status
CofO Issued on 2/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 ALFRED RAMIREZ
Corrections Issued 2/6/2025 ALFRED RAMIREZ
Quality Review Completed 2/13/2025 STEVEN KIM
Building Plans Picked Up 2/21/2025 APPLICANT
Applicant returned to address corrections 4/1/2025 ALFRED RAMIREZ
Applicant returned to address corrections 4/2/2025 ALFRED RAMIREZ
Plan Check Approved 4/4/2025 ALFRED RAMIREZ
Issued 4/4/2025 APPLICANT
No Progress 2/12/2026 EVAN COOPER
CofO in Progress 2/12/2026 EVAN COOPER
Permit Finaled 2/19/2026 RICHARD STEINBACH
CofO Issued 2/19/2026 RICHARD STEINBACH
Permit Finaled 2/19/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/27/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/27/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/27/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/27/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/27/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/27/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/27/2025 CARLOS AGUILERA
Sewer availability Cleared 2/27/2025 CARLOS AGUILERA
Low Impact Development (LID) Cleared 3/7/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 3/27/2025 BIAINA HARITUNIAN
GPI Written Notices Cleared 4/2/2025 ALFRED RAMIREZ
Grading Pre-Inspection Cleared 4/2/2025 ALFRED RAMIREZ

Contact Information

Contractor Totally Green Builders; Lic. No.: 1056343-B 14555 HAMLIN ST 3      VAN NUYS, CA 91411
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/30/2025 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 5/8/2025 Approved CARLOS MATAMOROS
Deputy Steel/Welding 5/15/2025 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Not Ready for Inspection MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Approved MEL KHACHATOURIAN
PLUMBING-Rough 7/7/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 7/10/2025 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 7/10/2025 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 7/14/2025 Corrections Issued MEL KHACHATOURIAN
HVAC-Rough 7/14/2025 Not Ready for Inspection MEL KHACHATOURIAN
Wood Frame 7/14/2025 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 7/17/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 7/17/2025 Approved ARAM AVEDISIAN
Green Building Rough 7/17/2025 Approved ARAM AVEDISIAN
HVAC-Rough 7/17/2025 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 7/17/2025 Approved ARAM AVEDISIAN
Insulation 7/21/2025 Conditional Approval MEL KHACHATOURIAN
Drywall Nailing 7/28/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 7/29/2025 Partial Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 8/5/2025 Approved CARLOS MATAMOROS
Shower Pan 8/5/2025 Approved CARLOS MATAMOROS
Pre-Inspection 12/19/2025 Approved EVAN COOPER
ELECTRICAL-Final 12/22/2025 Corrections Issued CARLOS MATAMOROS
Final 12/22/2025 Not Ready for Inspection CARLOS MATAMOROS
Green Building Final 12/22/2025 Approved CARLOS MATAMOROS
HVAC-Final 12/22/2025 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 12/22/2025 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 12/22/2025 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 12/22/2025 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 1/6/2026 Approved EVAN COOPER
HVAC-Final 1/6/2026 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 1/6/2026 Not Ready for Inspection EVAN COOPER
Service/Power Release 1/6/2026 Approved EVAN COOPER
Smoke Detectors 1/6/2026 Approved EVAN COOPER
Final 1/22/2026 Corrections Issued CARLOS MATAMOROS
HVAC-Final 1/22/2026 Corrections Issued CARLOS MATAMOROS
PLUMBING-Final 1/22/2026 Not Ready for Inspection CARLOS MATAMOROS
Gas Test 1/27/2026 Approved EVAN COOPER
HVAC-Final 1/27/2026 Approved EVAN COOPER
Final 1/28/2026 Conditional Approval EVAN COOPER
Special/Order Compliance 2/12/2026 Approved EVAN COOPER