8902 W GIBSON ST 90034

Certificate Information: 8902 W GIBSON ST 90034

Application / Permit
25014-20000-00371
Plan Check / Job No.
B25VN02092
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO (E) 1-STORY SFD AND REMOVE ATTACHED STORAGE/REC. ROOM TO CREATE A 1-STORY 69'-8" x 66'-10" SFD WITH ATTACHED TRELLIS PER ENGINEERING
Permit Issued
Issued on 5/6/2025
Issuing Office
Current Status
Issued on 5/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/28/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 ALFRED RAMIREZ
Corrections Issued 2/21/2025 ALFRED RAMIREZ
Quality Review Completed 2/21/2025 STEVEN KIM
Building Plans Picked Up 2/24/2025 APPLICANT
Applicant returned to address corrections 4/24/2025 ALFRED RAMIREZ
Plan Check Approved 5/6/2025 ALFRED RAMIREZ
Issued 5/6/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/28/2025 LEE GUILBEAUX
Sewer availability Cleared 2/28/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/28/2025 LEE GUILBEAUX
Low Impact Development (LID) Cleared 4/10/2025 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 4/15/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/28/2025 Approved EVAN COOPER
Pre-Inspection 6/17/2025 Approved EVAN COOPER
PLUMBING-Rough 7/18/2025 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 8/19/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 8/19/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Partial Approval EVAN COOPER
PLUMBING-Rough 10/30/2025 Partial Approval EVAN COOPER
Deputy Drilled-In Anchors 1/12/2026 Conditional Approval WILBER ROSALES
BUILDING-Rough-Frame 3/20/2026 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 3/20/2026 Corrections Issued WILBER ROSALES
Gas Test 3/20/2026 Corrections Issued WILBER ROSALES
Green Building Rough 3/20/2026 Not Ready for Inspection WILBER ROSALES
MERV13>=Rough 3/20/2026 Not Ready for Inspection WILBER ROSALES
PLUMBING-Rough 3/20/2026 Approved WILBER ROSALES
Sewer 3/20/2026 Approved WILBER ROSALES
Underground Mechanical 3/20/2026 Corrections Issued WILBER ROSALES
BUILDING-Rough-Frame 3/27/2026 Not Ready for Inspection WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 3/27/2026 Approved WILBER ROSALES
Gas Test 3/27/2026 Partial Approval WILBER ROSALES
MERV13>=Rough 3/27/2026 Not Ready for Inspection WILBER ROSALES
Underground Mechanical 3/27/2026 Partial Approval WILBER ROSALES
Shower Pan 5/11/2026 Partial Approval ANTHONY EGSON