8902 W GIBSON ST 90034
Certificate Information: 8902 W GIBSON ST 90034
- Application / Permit
- 25014-20000-00371
- Plan Check / Job No.
- B25VN02092
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL TO (E) 1-STORY SFD AND REMOVE ATTACHED STORAGE/REC. ROOM TO CREATE A 1-STORY 69'-8" x 66'-10" SFD WITH ATTACHED TRELLIS PER ENGINEERING
- Permit Issued
- Issued on 5/6/2025
- Issuing Office
- Current Status
- Issued on 5/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | ALFRED RAMIREZ |
| Corrections Issued | 2/21/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 2/21/2025 | STEVEN KIM |
| Building Plans Picked Up | 2/24/2025 | APPLICANT |
| Applicant returned to address corrections | 4/24/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 5/6/2025 | ALFRED RAMIREZ |
| Issued | 5/6/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/28/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/28/2025 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 4/10/2025 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/15/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/28/2025 | Approved | EVAN COOPER |
| Pre-Inspection | 6/17/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 7/18/2025 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 8/19/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 8/19/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 10/30/2025 | Partial Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 1/12/2026 | Conditional Approval | WILBER ROSALES |
| BUILDING-Rough-Frame | 3/20/2026 | Corrections Issued | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Corrections Issued | WILBER ROSALES |
| Gas Test | 3/20/2026 | Corrections Issued | WILBER ROSALES |
| Green Building Rough | 3/20/2026 | Not Ready for Inspection | WILBER ROSALES |
| MERV13>=Rough | 3/20/2026 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Rough | 3/20/2026 | Approved | WILBER ROSALES |
| Sewer | 3/20/2026 | Approved | WILBER ROSALES |
| Underground Mechanical | 3/20/2026 | Corrections Issued | WILBER ROSALES |
| BUILDING-Rough-Frame | 3/27/2026 | Not Ready for Inspection | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2026 | Approved | WILBER ROSALES |
| Gas Test | 3/27/2026 | Partial Approval | WILBER ROSALES |
| MERV13>=Rough | 3/27/2026 | Not Ready for Inspection | WILBER ROSALES |
| Underground Mechanical | 3/27/2026 | Partial Approval | WILBER ROSALES |
| Shower Pan | 5/11/2026 | Partial Approval | ANTHONY EGSON |