14932-14934 W MARTHA ST 91411

Certificate Information: 14932-14934 W MARTHA ST 91411

Application / Permit
25014-20000-00356
Plan Check / Job No.
B25VN01986
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL WITH 2-STORY ADDITIONS, CONVERSION OF ATTACHED PATIO COVER TO BE PART OF SFD AND CONVERSION OF (E) ATTACHED GARAGE INTO A (N) JUNIOR ACCESSORY DWELLING UNIT TO COMPLY CA Govt. Code 65852.2(e)(1)(A) and 65852.22 AND ADDITION OF REAR ATTACHED PATIO COVER PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 5/9/2025
Issuing Office
Valley
Current Status
Issued on 5/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/27/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 ALFRED RAMIREZ
Corrections Issued 2/8/2025 ALFRED RAMIREZ
Quality Review Completed 2/18/2025 STEVEN KIM
Building Plans Picked Up 2/18/2025 APPLICANT
Plan Check Approved 3/3/2025 ALFRED RAMIREZ
Plan Check Approved 3/3/2025 ALFRED RAMIREZ
Issued 5/9/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/21/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 2/21/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 2/21/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/21/2025 BIAINA HARITUNIAN

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/20/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/9/2025 Partial Approval DAVID ANDERSON
PLUMBING-Rough 7/9/2025 Corrections Issued DAVID ANDERSON
Sewer 7/9/2025 Approved DAVID ANDERSON
PLUMBING-Rough 7/11/2025 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Partial Approval RYAN SALAZAR
Green Building Rough 7/21/2025 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 7/21/2025 Partial Approval RYAN SALAZAR
Deputy Wood Construction 9/3/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Partial Approval RYAN SALAZAR
Wood Frame 9/3/2025 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 10/15/2025 Approved RYAN SALAZAR
Green Building Rough 10/15/2025 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 10/15/2025 Approved RYAN SALAZAR
Insulation 10/21/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/21/2025 Partial Approval RYAN SALAZAR
Shower Pan 10/21/2025 Approved RYAN SALAZAR
Drywall Nailing 11/4/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 11/4/2025 Approved LOUIS ESCOTO
Service/Power Release 11/6/2025 No Access for Inspection OGANES TARAKHCHYAN
Service/Power Release 11/10/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 4/29/2026 Corrections Issued VINCENT HANLEY
Final 4/29/2026 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 4/29/2026 Approved VINCENT HANLEY
Green Building Final 4/29/2026 Approved VINCENT HANLEY
HVAC-Final 4/29/2026 Corrections Issued VINCENT HANLEY
PLUMBING-Final 4/29/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/29/2026 SGSOV Approved VINCENT HANLEY
Smoke Detectors 4/29/2026 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Final 5/28/2026 Approved VINCENT HANLEY
Final 5/28/2026 Corrections Issued VINCENT HANLEY
HVAC-Final 5/28/2026 Approved VINCENT HANLEY
Service/Power Release 5/28/2026 Approved VINCENT HANLEY
Smoke Detectors 5/28/2026 Approved VINCENT HANLEY