7300 N CLEON AVE 91352
Certificate Information: 7300 N CLEON AVE 91352
- Application / Permit
- 25014-20000-00294
- Plan Check / Job No.
- B25VN01593
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 18'6" X 14'6" ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING TO ADD A NEW BEDROOM. WORK DONE PER WFPP.
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 5/18/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 1/23/2025 | ARAMIK SHAHMIRZAIAN |
| Applicant returned to address corrections | 3/10/2025 | MADISON ODELL |
| Plan Check Approved | 3/20/2025 | NAREG ATARIAN |
| Issued | 3/20/2025 | APPLICANT |
| CofO in Progress | 5/18/2026 | ROBERTO PALACIOS-LOPEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 2/24/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 3/5/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 5/27/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/28/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/18/2025 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 6/18/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/18/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/24/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/11/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 8/26/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 8/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 9/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 9/5/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 9/16/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 2/9/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/9/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 2/9/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 2/9/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 2/9/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/9/2026 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/9/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 4/13/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/13/2026 | Approved | ROBERTO PALACIOS-LOPEZ |