24206 W HARTLAND ST 91307

Certificate Information: 24206 W HARTLAND ST 91307

Application / Permit
25014-20000-00283
Plan Check / Job No.
B25VN01476
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Remodel and irregular shaped addition of 12' x 49' 10" at the South portion of the lot.
Permit Issued
Issued on 3/21/2025
Issuing Office
Current Status
CofO Issued on 2/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2025 APPLICANT
Assigned to Plan Check Engineer 1/27/2025 NAREG ATARIAN
Corrections Issued 1/28/2025 NAREG ATARIAN
Applicant returned to address corrections 2/10/2025 NAREG ATARIAN
Applicant returned to address corrections 2/13/2025 NAREG ATARIAN
Plan Check Approved 2/18/2025 NAREG ATARIAN
Issued 3/21/2025 APPLICANT
CofO in Progress 11/1/2025 TROY SANDERS
Permit Finaled 2/20/2026 JOHN JANSON
CofO Issued 2/20/2026 JOHN JANSON
Permit Finaled 2/20/2026 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/4/2025 EDGAR ALCARAZ
Sewer availability Cleared 2/4/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/14/2025 EDGAR ALCARAZ

Contact Information

Architect Erlich,, Ayal; Lic. No.: NA36241       ,
Contractor U S Developer & Property Inc; Lic. No.: 906346-B       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/4/2025 Approved GEVORK IPCHYAN
Deputy Drilled-In Anchors 4/10/2025 Conditional Approval TROY SANDERS
Footing/Foundation/Slab 4/14/2025 Approved JEFFREY HARTLINE
Sewer 4/14/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Corrections Issued GEVORK IPCHYAN
BUILDING-Rough-Frame 5/16/2025 Approved TROY SANDERS
ELECTRICAL-Rough 5/16/2025 Not Ready for Inspection TROY SANDERS
Green Building Rough 5/16/2025 Not Ready for Inspection TROY SANDERS
HVAC-Rough 5/16/2025 Approved TROY SANDERS
PLUMBING-Rough 5/16/2025 Not Ready for Inspection TROY SANDERS
Deputy Wood Construction 5/19/2025 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 5/23/2025 Approved TROY SANDERS
Interior/Exterior Lathing 5/23/2025 Partial Approval TROY SANDERS
PLUMBING-Rough 5/23/2025 Approved TROY SANDERS
Drywall Nailing 5/30/2025 Approved TROY SANDERS
Green Building Rough 5/30/2025 Approved TROY SANDERS
Shower Pan 6/13/2025 Approved TROY SANDERS
Final 10/24/2025 Not Ready for Inspection TROY SANDERS
Green Building Final 10/24/2025 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Approved TROY SANDERS
Smoke Detectors 10/24/2025 Approved TROY SANDERS
ELECTRICAL-Final 10/31/2025 Approved TROY SANDERS
Final 10/31/2025 OK to Issue CofO TROY SANDERS
Green Building Final 10/31/2025 Approved TROY SANDERS
HVAC-Final 10/31/2025 Approved TROY SANDERS
PLUMBING-Final 10/31/2025 Approved TROY SANDERS