9345-9347 N DEBRA AVE 91343

Certificate Information: 9345-9347 N DEBRA AVE 91343

Application / Permit
25014-20000-00280
Plan Check / Job No.
B25VN01464
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND CONVERT PORTION OF EX. SFD INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33
Permit Issued
Issued on 4/24/2025
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2025 APPLICANT
Assigned to Plan Check Engineer 1/27/2025 ROSENDO MEDINA
Corrections Issued 1/28/2025 ROSENDO MEDINA
Applicant returned to address corrections 4/9/2025 ROSENDO MEDINA
Plan Check Approved 4/23/2025 KAMYAR EMAMI
Issued 4/24/2025 APPLICANT
CofO in Progress 3/3/2026 KIRK SANDERS
CofO Issued 6/4/2026 RUBEN SALAS
Permit Finaled 6/4/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/15/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 4/15/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/16/2025 BIAINA HARITUNIAN
Sewer availability Cleared 4/16/2025 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 4/16/2025 ROBERT PINA

Contact Information

Contractor Bespoke Designs & Build Inc; Lic. No.: 971955-B       ,
Contractor Creative Construction & Design; Lic. No.: 971955-B       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240
Engineer Carrillo,, Jesus Eduardo; Lic. No.: NA77737       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/28/2025 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 5/1/2025 Corrections Issued SALVADOR MARTINEZ
Special/Order Compliance 5/1/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/22/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 5/22/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 5/22/2025 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 5/22/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 5/22/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 5/28/2025 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 5/28/2025 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 5/28/2025 Not Ready for Inspection SALVADOR MARTINEZ
Shower Pan 5/28/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/2/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 6/2/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 6/2/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 6/2/2025 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 6/2/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 6/2/2025 Corrections Issued SALVADOR MARTINEZ
Shower Pan 6/2/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/16/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 7/16/2025 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 7/16/2025 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 7/16/2025 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 7/18/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Insulation 7/18/2025 Partial Approval GAREN HAYRAPETYAN
Interior/Exterior Lathing 7/18/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Interior/Exterior Lathing 7/25/2025 Approved MICHAEL CORTEZ
Floor/Roof Diaphrgm/Shear Wall 7/31/2025 Partial Approval GAREN HAYRAPETYAN
Interior/Exterior Lathing 8/5/2025 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Rough 8/20/2025 Approved SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 8/20/2025 Partial Approval SALVADOR MARTINEZ
Underground Mechanical 8/20/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/22/2025 Conditional Approval GAREN HAYRAPETYAN
Green Building Rough 8/22/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 8/22/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 8/26/2025 Approved GAREN HAYRAPETYAN
Insulation 8/26/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 9/2/2025 Approved ROBERTO PALACIOS-LOPEZ
Sewer 10/8/2025 Approved CHRISTOPHER MORFIN
Footing/Foundation/Slab 10/20/2025 Approved GAREN HAYRAPETYAN
Insulation 10/23/2025 Approved WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 10/30/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 11/5/2025 Approved GAREN HAYRAPETYAN
Final 11/5/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 11/5/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 11/5/2025 Approved GAREN HAYRAPETYAN
Final 11/19/2025 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Final 2/9/2026 Approved GAREN HAYRAPETYAN
HVAC-Final 2/9/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 2/9/2026 Approved GAREN HAYRAPETYAN
Final 3/2/2026 OK to Issue CofO KIRK SANDERS