4654-4656 N COLUMBUS AVE 91403
Certificate Information: 4654-4656 N COLUMBUS AVE 91403
- Application / Permit
- 25014-20000-00272
- Plan Check / Job No.
- B25VN01430
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION (ONLY 2'0" WALL TO REMAIN) TO MAKE A 68'7-1/2"X49'9-1/2" 2-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) (NFPA 13-D FIRE SPRINKLERS REQUIRED THROUGHOUT)
- Permit Issued
- Issued on 3/19/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | MARVEL DELACRUZ |
| Corrections Issued | 1/28/2025 | MARVEL DELACRUZ |
| Quality Review Completed | 1/30/2025 | JASON HEALEY |
| Building Plans Picked Up | 2/6/2025 | APPLICANT |
| Applicant returned to address corrections | 3/14/2025 | MARVEL DELACRUZ |
| Plan Check Approved | 3/18/2025 | MARVEL DELACRUZ |
| Issued | 3/19/2025 | APPLICANT |
| CofO in Progress | 10/20/2025 | JACK KARGODORIAN |
| CofO in Progress | 11/13/2025 | THOMAS COWAN |
| Permit Finaled | 11/13/2025 | RUBEN SALAS |
| CofO Issued | 11/13/2025 | RUBEN SALAS |
| Permit Finaled | 11/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/7/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/7/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/10/2025 | Approved | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 4/11/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 4/11/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/14/2025 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 4/17/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/17/2025 | Approved | JACK KARGODORIAN |
| Deputy Wood Construction | 4/30/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2025 | Partial Approval | JACK KARGODORIAN |
| Structural Steel Frame | 4/30/2025 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/7/2025 | Partial Inspection | JAVIER RAMOS JR |
| Deputy Wood Construction | 5/7/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Partial Inspection | JAVIER RAMOS JR |
| Structural Steel Frame | 5/7/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Special/Order Compliance | 5/23/2025 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/2/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Partial Approval | JACK KARGODORIAN |
| Gas Test | 6/2/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 6/2/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 6/2/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 6/9/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 6/9/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 6/9/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 6/11/2025 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 6/16/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Pre-Inspection | 6/16/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/18/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 6/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 6/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Drywall Nailing | 6/20/2025 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 6/23/2025 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 6/23/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 6/24/2025 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 6/26/2025 | Partial Approval | JACK KARGODORIAN |
| Insulation | 6/30/2025 | Approved | JACK KARGODORIAN |
| Shower Pan | 6/30/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/8/2025 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 7/8/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/8/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 7/8/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Drywall Nailing | 7/11/2025 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 7/11/2025 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 7/15/2025 | Approved | JACK KARGODORIAN |
| Final | 10/6/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Final | 10/6/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 10/6/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 10/6/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 10/6/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 10/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 10/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 10/7/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/14/2025 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/15/2025 | Approved | JACK KARGODORIAN |
| Final | 10/15/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 10/15/2025 | Approved | JACK KARGODORIAN |
| HVAC-Final | 10/15/2025 | Approved | JACK KARGODORIAN |
| Service/Power Release | 10/15/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 10/15/2025 | Approved | JACK KARGODORIAN |
| Pre-Inspection | 10/17/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 10/20/2025 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 10/20/2025 | Approved | JACK KARGODORIAN |