4843 N AGNES AVE 91607
Certificate Information: 4843 N AGNES AVE 91607
- Application / Permit
- 25014-20000-00267
- Plan Check / Job No.
- B25VN01391
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR SHAPE (47'-10"x 40') ADDITION TO REAR SIDE OF (E) SFD, ADDITION OF IRREGULAR SHAPE (12'-6" x 7'-9") ADDITION TO FRONT OF SFD AND MAJOR REMODEL OF (E) SFD AND CONVERT (E) DINING ROOM TO GARAGE. (18'-10"x18'-10") WITH (8'-2" X 7'-9") ADDITION TO GARAGE. ADDITION OF (22'-6"X8') PORCH IN BACK OF SFD. *NFPA 13D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/17/2025
- Issuing Office
- Valley
- Current Status
- Issued on 3/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | EDWARD MEHRABIAN |
| Corrections Issued | 1/25/2025 | EDWARD MEHRABIAN |
| Quality Review Completed | 1/27/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 1/29/2025 | APPLICANT |
| Plan Check Approved | 3/14/2025 | EDWARD MEHRABIAN |
| Issued | 3/17/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 1/29/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/29/2025 | EDGAR ALCARAZ |
| Permit | Cleared | 2/27/2025 | CARLOS AGUILERA |
| Specific Plan | Cleared | 2/27/2025 | JOANNA MARROQUIN |
| ZI | Cleared | 2/27/2025 | JOANNA MARROQUIN |
| ZI | Cleared | 2/27/2025 | JOANNA MARROQUIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 4/24/2025 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/25/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/1/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/15/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/15/2025 | Partial Approval | JAVIER RAMOS JR |
| Special/Order Compliance | 5/15/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/30/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/15/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 7/22/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/22/2025 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 7/22/2025 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 7/23/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/4/2025 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 8/8/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 8/22/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/2/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 9/2/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 9/5/2025 | Corrections Issued | JAVIER RAMOS JR |
| Shower Pan | 9/9/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/19/2025 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Final | 1/20/2026 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 1/20/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/5/2026 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 2/5/2026 | Approved | JAVIER RAMOS JR |
| Final | 2/23/2026 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 2/23/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/23/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/23/2026 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/23/2026 | Approved | JAVIER RAMOS JR |