10450 W RAINIER ST 91352

Certificate Information: 10450 W RAINIER ST 91352

Application / Permit
25014-20000-00259
Plan Check / Job No.
B25VN01352
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, 38'-11" X 22'-2" ADDITION TO (E) SFD. FIRE SPRINKLER (NFPA-13D) IS REQUIRED THROUGHOUT.
Permit Issued
Issued on 3/13/2025
Issuing Office
Valley
Current Status
CofO in Progress on 6/4/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/21/2025 APPLICANT
Assigned to Plan Check Engineer 1/29/2025 ARTIN ZARUKIAN
Corrections Issued 2/3/2025 ARTIN ZARUKIAN
Building Plans Picked Up 2/4/2025 APPLICANT
Applicant returned to address corrections 2/18/2025 KAMYAR EMAMI
Plan Check Approved 2/21/2025 JESSE ARELLANO
Issued 3/13/2025 APPLICANT
CofO in Progress 6/4/2026 DAVID ANDERSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/11/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 2/11/2025 SAFA JAVANMARDI
Sewer availability Cleared 2/11/2025 CARLOS AGUILERA

Contact Information

Contractor Advanced General Construction; Lic. No.: 951083-B 6545 HAZELTINE AVE 108      VAN NUYS, CA 91401
Engineer Li,, Dacheng D; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/3/2025 Approved DAVID ANDERSON
Footing/Foundation/Slab 4/9/2025 Not Ready for Inspection DAVID ANDERSON
Deputy Drilled-In Anchors 4/10/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/11/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Partial Approval DAVID ANDERSON
PLUMBING-Rough 4/25/2025 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Partial Approval DAVID ANDERSON
Insulation 5/5/2025 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Partial Approval DAVID ANDERSON
Deputy Wood Construction 8/5/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/20/2025 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 9/26/2025 Not Ready for Inspection DAVID ANDERSON
HVAC-Rough 9/26/2025 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 9/26/2025 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 9/30/2025 Partial Approval DAVID ANDERSON
Shower Pan 9/30/2025 Approved DAVID ANDERSON
Insulation 10/3/2025 Not Ready for Inspection MICHAEL CORTEZ
HVAC-Rough 10/7/2025 Approved DAVID ANDERSON
PLUMBING-Rough 10/7/2025 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 10/10/2025 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 10/17/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 10/17/2025 Approved DAVID ANDERSON
Green Building Rough 10/17/2025 Approved DAVID ANDERSON
MERV13>=Rough 10/17/2025 Approved DAVID ANDERSON
PLUMBING-Rough 10/17/2025 Approved DAVID ANDERSON
Insulation 10/20/2025 Approved DAVID ANDERSON
Drywall Nailing 11/14/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/25/2025 Not Ready for Inspection DAVID ANDERSON
Verify Sprinkler Sign Off 11/25/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 12/4/2025 Approved LOUIS ESCOTO
Pre-Inspection 3/13/2026 Approved DAVID ANDERSON
Final 5/29/2026 Corrections Issued DAVID ANDERSON
Green Building Final 5/29/2026 Approved DAVID ANDERSON
MERV13>=Final 5/29/2026 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Approved DAVID ANDERSON
Smoke Detectors 5/29/2026 Approved DAVID ANDERSON
Final 6/3/2026 OK to Issue CofO DAVID ANDERSON