23711 W CANZONET ST 91367
Certificate Information: 23711 W CANZONET ST 91367
- Application / Permit
- 25014-20000-00252
- Plan Check / Job No.
- B25VN01312
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION AND REMODEL OF THE EXISTING SINGLE FAMILY DWELLING - PER ENGINEER
- Permit Issued
- Issued on 2/11/2025
- Issuing Office
- Current Status
- CofO Issued on 4/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2025 | DANIEL ABRAMYAN |
| Corrections Issued | 1/25/2025 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 2/4/2025 | ISIS ARGUETA |
| Applicant returned to address corrections | 2/6/2025 | ISIS ARGUETA |
| Plan Check Approved | 2/9/2025 | ISIS ARGUETA |
| Issued | 2/11/2025 | APPLICANT |
| CofO in Progress | 7/22/2025 | TROY SANDERS |
| Permit Finaled | 4/11/2026 | MICHAEL PELHAM |
| CofO Issued | 4/11/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/11/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/28/2025 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 1/30/2025 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/4/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Rough | 3/19/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 4/3/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Partial Approval | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 4/3/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 4/3/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 4/9/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 4/9/2025 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 4/9/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 4/23/2025 | Approved | GEVORK IPCHYAN |
| Shower Pan | 4/23/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/28/2025 | Partial Approval | GEVORK IPCHYAN |
| Green Building Rough | 5/6/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 5/6/2025 | Corrections Issued | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 6/4/2025 | Partial Approval | GEVORK IPCHYAN |
| Drywall Nailing | 7/21/2025 | Approved | TROY SANDERS |
| Final | 7/21/2025 | OK to Issue CofO | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/21/2025 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 7/21/2025 | Approved | TROY SANDERS |