19617 W PINE VALLEY AVE 91326

Certificate Information: 19617 W PINE VALLEY AVE 91326

Application / Permit
25014-20000-00225
Plan Check / Job No.
B25VN01188
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Remodel to (E) 2-Story SFD w/attached garage and ground floor addition and new covered patio, NFPA 13D fire sprinklers to be provided
Permit Issued
Issued on 4/24/2025
Issuing Office
Current Status
Issued on 4/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/20/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 DAVID CASTILLO
Corrections Issued 2/4/2025 DAVID CASTILLO
Quality Review Completed 2/12/2025 CHIHARU SUZUKI
Applicant returned to address corrections 4/15/2025 DAVID CASTILLO
Plan Check Approved 4/23/2025 DAVID CASTILLO
Issued 4/24/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/19/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/19/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/19/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/19/2025 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 2/19/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/19/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/22/2025 CARLOS AGUILERA
Hydrant and Access approval Cleared 4/3/2025 JERRY KAO
Grading Pre-Inspection Cleared 4/15/2025 DAVID CASTILLO

Contact Information

Architect Song,, Michael; Lic. No.: C32566 255 S LA BREA AVE      INGLEWOOD, CA 90301
Contractor Designer Kitchens; Lic. No.: 860365-B       ,
Contractor High Touch Inc; Lic. No.: 860365-B       ,
Engineer Kazemi,, Milad; Lic. No.: NA92143       ,
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/12/2025 Partial Approval JEFFREY PARD
Deputy Drilled-In Anchors 7/1/2025 Conditional Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 7/9/2025 Approved STEVEN BACK
Deputy Reinf. Concrete 7/11/2025 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 10/1/2025 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 11/14/2025 Not Ready for Inspection KRISTEN CAUSEY
ELECTRICAL-Rough 11/14/2025 Not Ready for Inspection KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 11/14/2025 Partial Approval KRISTEN CAUSEY
HVAC-Rough 11/14/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 11/14/2025 Conditional Approval KRISTEN CAUSEY
Verify Sprinkler Sign Off 11/14/2025 Not Ready for Inspection KRISTEN CAUSEY
Deputy Wood Construction 11/18/2025 Conditional Approval STEVEN BACK
Deputy Wood Construction 11/20/2025 Approved STEVEN BACK
ELECTRICAL-Rough 11/20/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/20/2025 Approved STEVEN BACK
PLUMBING-Rough 11/20/2025 Approved STEVEN BACK
Special/Order Compliance 11/20/2025 Corrections Issued STEVEN BACK
Verify Sprinkler Sign Off 11/20/2025 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 12/15/2025 Approved JEFFREY PARD
Pre-Inspection 12/17/2025 Partial Approval STEVEN BACK
Verify Sprinkler Sign Off 12/17/2025 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 1/14/2026 Approved JEFFREY PARD
Verify Sprinkler Sign Off 1/14/2026 Approved JEFFREY PARD
Insulation 1/22/2026 Approved CHRIS CHRISTENSEN
Drywall Nailing 1/30/2026 Corrections Issued JEFFREY PARD
Drywall Nailing 2/5/2026 Approved JEFFREY PARD
Interior/Exterior Lathing 2/19/2026 Approved STEVEN BACK
Shower Pan 2/19/2026 Approved STEVEN BACK