13550 W ADDISON ST 91423
Certificate Information: 13550 W ADDISON ST 91423
- Application / Permit
- 25014-20000-00208
- Plan Check / Job No.
- B25VN01082
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF SFD TO ENLARGE GARAGE AND ADD TO GARAGE. ADD 41 SF AT FRONT AND 820 SF AT REAR OF SFD. ADD 17' X 26' SOLID ROOF PATIO COVER AND 7' X 42'-11" LATTICE ROOF PATIO COVER AND REMODEL (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 3/3/2025
- Issuing Office
- Current Status
- Issued on 3/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | RAPHAEL ROSAS |
| Corrections Issued | 1/28/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 1/28/2025 | STEVEN KIM |
| Building Plans Picked Up | 1/29/2025 | APPLICANT |
| Applicant returned to address corrections | 2/25/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 3/3/2025 | RAPHAEL ROSAS |
| Issued | 3/3/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/31/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 1/31/2025 | BIAINA HARITUNIAN |
| ZI | Cleared | 2/3/2025 | BRENNEN OBETO |
| Trees in Parkway | Cleared | 2/18/2025 | BRANDON WONG |
| Permit | Cleared | 2/19/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/10/2025 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 6/16/2025 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 6/18/2025 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/18/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 8/22/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/14/2025 | No Access for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Rough | 10/14/2025 | No Access for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/17/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 10/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/17/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 12/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/23/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/23/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/23/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/23/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/23/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/27/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 1/27/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 1/27/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 1/27/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 1/30/2026 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/5/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/5/2026 | Approved | MISAEL ESPARZA |
| Green Building Rough | 2/5/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 2/5/2026 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/5/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 2/5/2026 | Approved | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 2/5/2026 | Approved | MISAEL ESPARZA |
| Wood Frame | 2/5/2026 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 2/17/2026 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 3/13/2026 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 3/13/2026 | Partial Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Test | 3/13/2026 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/13/2026 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/25/2026 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 3/25/2026 | Approved | MISAEL ESPARZA |
| Wood Frame | 3/25/2026 | Approved | MISAEL ESPARZA |
| Insulation | 4/1/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 4/29/2026 | Approved | MISAEL ESPARZA |
| Insulation | 4/29/2026 | Approved | MISAEL ESPARZA |
| Special/Order Compliance | 4/29/2026 | Corrections Issued | MISAEL ESPARZA |
| Drywall Nailing | 5/12/2026 | Approved | MISAEL ESPARZA |