10359 W FLOWERDALE CT 91352

Certificate Information: 10359 W FLOWERDALE CT 91352

Application / Permit
25014-20000-00202
Plan Check / Job No.
B24VN27349
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST & 2ND FLR ADDT'S TO (E) 1-STORY SFD W/ ATTACHED GARAGE: EXPAND GARAGE (23'-7" X 10'), ADD 392.2SF AT 1ST FLR & ADD (N) 2ND FLR (1505SF); MAJOR REMODEL (NFPA-13D FIRE SPRINKLERS THROUGHOU) ** ePlan**
Permit Issued
Issued on 4/10/2025
Issuing Office
Current Status
Issued on 4/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/16/2025 APPLICANT
Assigned to Plan Check Engineer 1/23/2025 NILOOFAR MEHRAIN
Corrections Issued 1/26/2025 NILOOFAR MEHRAIN
Quality Review Completed 1/29/2025 JASON HEALEY
Applicant returned to address corrections 3/12/2025 NILOOFAR MEHRAIN
Plan Check Approved 3/13/2025 NILOOFAR MEHRAIN
Plan Check Approved 3/27/2025 NILOOFAR MEHRAIN
Plan Check Approved 4/8/2025 NILOOFAR MEHRAIN
Plan Check Approved 4/8/2025 NILOOFAR MEHRAIN
Issued 4/10/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/6/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/6/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/6/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/6/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/6/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/6/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/6/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/7/2025 LEE GUILBEAUX
Sewer availability Cleared 2/7/2025 LEE GUILBEAUX
Miscellaneous Cleared 2/12/2025 DALIA MOKAYED
Hydrant and Access approval Cleared 2/19/2025 PATRICK PEREZ
GPI Written Notices Cleared 3/12/2025 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 3/12/2025 NILOOFAR MEHRAIN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/28/2025 Approved DAVID ANDERSON
PLUMBING-Rough 6/16/2025 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 6/23/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/24/2025 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 10/27/2025 Not Ready for Inspection DAVID ANDERSON
Final 10/27/2025 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 10/27/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/27/2025 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 10/27/2025 Not Ready for Inspection DAVID ANDERSON
Verify Sprinkler Sign Off 10/27/2025 Corrections Issued DAVID ANDERSON
HVAC-Rough 11/5/2025 Corrections Issued DAVID ANDERSON
HVAC-Rough 11/14/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/14/2025 Partial Approval DAVID ANDERSON
PLUMBING-Rough 11/14/2025 Corrections Issued DAVID ANDERSON
Sewer 11/14/2025 Partial Approval DAVID ANDERSON
PLUMBING-Rough 11/17/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 11/18/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 11/25/2025 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 11/25/2025 Approved DAVID ANDERSON
Insulation 12/11/2025 Corrections Issued DAVID ANDERSON
Shower Pan 12/11/2025 Not Ready for Inspection DAVID ANDERSON
Insulation 12/15/2025 Approved DAVID ANDERSON
Shower Pan 12/15/2025 Approved DAVID ANDERSON
Drywall Nailing 12/22/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 1/28/2026 Approved OGANES TARAKHCHYAN