18008-18010 W SANDY CAPE DR 90272
Certificate Information: 18008-18010 W SANDY CAPE DR 90272
- Application / Permit
- 25014-20000-00201
- Plan Check / Job No.
- B25VN01054
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) RECROOM ( 31'x 25'-6" )TO JADU PER GCS 66322(a)(1) AND 66333. NEW EXTERIOR STAIRCASE WITH NEW (8'X4') LANDING AREA . REFRAME (E) COVERED PORCH (13'-5"x 3') IN FRONT OF HOUSE. "COMPLY WITH DEPARTMENT ORDER effective date 09/09/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" JADU AFFADAVIT # 20250389027
- Permit Issued
- Issued on 6/12/2025
- Issuing Office
- Current Status
- Issued on 6/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | EDWARD MEHRABIAN |
| Corrections Issued | 2/13/2025 | EDWARD MEHRABIAN |
| Quality Review Completed | 2/14/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 2/20/2025 | APPLICANT |
| Applicant returned to address corrections | 6/4/2025 | EDWARD MEHRABIAN |
| Plan Check Approved | 6/12/2025 | EDWARD MEHRABIAN |
| Issued | 6/12/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/27/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2025 | DARIN LAM |
| Sewer availability | Cleared | 2/27/2025 | DARIN LAM |
| Miscellaneous | Cleared | 3/5/2025 | DALIA MOKAYED |
| ZA Case | Cleared | 3/5/2025 | DALIA MOKAYED |
| Coastal Zone | Cleared | 5/28/2025 | DALIA MOKAYED |
| ZI | Cleared | 5/28/2025 | DALIA MOKAYED |
| Grading Pre-Inspection | Cleared | 6/4/2025 | EDWARD MEHRABIAN |
Contact Information
| Contractor | Anytime Remodeling And Design; Lic. No.: 1025867-B | 13300 VICTORY BLVD #316 VAN NUYS, CA 91401 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/13/2026 | Not Ready for Inspection | RYAN BARNES |
| Drywall Nailing | 3/13/2026 | Not Ready for Inspection | RYAN BARNES |
| Final | 3/13/2026 | Not Ready for Inspection | RYAN BARNES |
| Footing/Foundation/Slab | 3/13/2026 | Not Ready for Inspection | RYAN BARNES |
| Green Building Final | 3/13/2026 | Not Ready for Inspection | RYAN BARNES |
| Green Building Rough | 3/13/2026 | Not Ready for Inspection | RYAN BARNES |
| Pre-Inspection | 3/13/2026 | Not Ready for Inspection | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Not Ready | RYAN BARNES |
| Smoke Detectors | 3/13/2026 | Not Ready for Inspection | RYAN BARNES |