20249 W PARTHENIA ST 91306
Certificate Information: 20249 W PARTHENIA ST 91306
- Application / Permit
- 25014-20000-00197
- Plan Check / Job No.
- B25VN01026
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20'-7" X 10'-6" ADDITION TO (E) DETACHED GARAGE & CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1). CONSTRUCTION DESIGN PER ENGR
- Permit Issued
- Issued on 4/29/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 1/23/2025 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 4/11/2025 | HAYATO TSUCHIYA |
| Plan Check Approved | 4/25/2025 | GIOVANNY CHAVEZ |
| Issued | 4/29/2025 | APPLICANT |
| CofO in Progress | 1/27/2026 | CHRIS CHRISTENSEN |
| Permit Finaled | 2/23/2026 | JOHN JANSON |
| CofO Issued | 2/23/2026 | JOHN JANSON |
| Permit Finaled | 2/23/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/19/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 2/21/2025 | RYAN CASTRO |
| Construction near power lines | Cleared | 4/4/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 6047 TAMPA AVE SUITE 304 TARZANA, CA 91356 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Partial Approval | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 6/10/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 8/12/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 8/12/2025 | Approved | JEFFREY HARTLINE |
| Sewer | 8/12/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 8/19/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 8/19/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 8/19/2025 | Partial Approval | JEFFREY HARTLINE |
| Insulation | 8/25/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 9/3/2025 | Approved | JEFFREY HARTLINE |
| Shower Pan | 9/3/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 9/9/2025 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Final | 1/16/2026 | Approved | CHRIS CHRISTENSEN |
| Final | 1/16/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/16/2026 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 1/16/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 1/16/2026 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 1/16/2026 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 1/16/2026 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 1/16/2026 | Approved | CHRIS CHRISTENSEN |
| Final | 1/26/2026 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 1/26/2026 | Approved | CHRIS CHRISTENSEN |