3791 S EDGEHILL DR 90018

Certificate Information: 3791 S EDGEHILL DR 90018

Application / Permit
25014-20000-00180
Plan Check / Job No.
B25VN00953
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD WITH ADDITION AND (N) PATIO
Permit Issued
Issued on 2/6/2025
Issuing Office
Current Status
CofO Issued on 11/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2025 APPLICANT
Assigned to Plan Check Engineer 1/17/2025 ARTIN ZARUKIAN
Corrections Issued 1/18/2025 ARTIN ZARUKIAN
Building Plans Picked Up 1/21/2025 APPLICANT
Plan Check Approved 2/6/2025 ALEC MOUSAKHANIAN
Issued 2/6/2025 APPLICANT
CofO in Progress 10/30/2025 LUIS CASTRO
Permit Finaled 11/9/2025 DEROLD HAUFF
CofO Issued 11/9/2025 DEROLD HAUFF
Permit Finaled 11/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/4/2025 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 2/4/2025 CHRISTINA BRACO
Sewer availability Cleared 2/4/2025 CHRISTINA BRACO

Contact Information

Contractor Bela Development; Lic. No.: 1038287-B 1023 1/2 ABBOT KINNEY BLVD      VENICE, CA 90291
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/14/2025 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 3/14/2025 Not Ready for Inspection BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 3/17/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/27/2025 Partial Approval LUIS CASTRO
Green Building Rough 3/27/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 3/27/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Partial Approval LUIS CASTRO
Insulation 4/3/2025 Partial Approval LUIS CASTRO
Deputy Drilled-In Anchors 4/17/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 6/16/2025 Approved LUIS CASTRO
HVAC-Rough 6/16/2025 Approved LUIS CASTRO
PLUMBING-Rough 6/16/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 6/20/2025 Partial Approval LUIS CASTRO
Shower Pan 6/20/2025 Approved LUIS CASTRO
Wood Frame 6/20/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Not Ready for Inspection ANTHONY RAMOS
Insulation 6/25/2025 Corrections Issued ANTHONY RAMOS
Interior/Exterior Lathing 6/27/2025 Approved RONNIE MEDINA
Drywall Nailing 7/1/2025 Approved LUIS CASTRO
Green Building Rough 7/1/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 10/14/2025 Approved LUIS CASTRO
Final 10/14/2025 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 10/14/2025 Approved LUIS CASTRO
Green Building Final 10/14/2025 Not Ready for Inspection LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 10/14/2025 Approved LUIS CASTRO
ELECTRICAL-Final 10/29/2025 Approved LUIS CASTRO
Final 10/29/2025 OK to Issue CofO LUIS CASTRO
Green Building Final 10/29/2025 Approved LUIS CASTRO
HVAC-Final 10/29/2025 Approved LUIS CASTRO
PLUMBING-Final 10/29/2025 Approved LUIS CASTRO