12596 W DEBELL ST 91331
Certificate Information: 12596 W DEBELL ST 91331
- Application / Permit
- 25014-20000-00175
- Plan Check / Job No.
- B25VN00869
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) single family dwelling
- Permit Issued
- Issued on 2/25/2025
- Issuing Office
- Current Status
- Issued on 2/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2025 | ALEXANDER JOO |
| Corrections Issued | 1/23/2025 | ALEXANDER JOO |
| Applicant returned to address corrections | 2/15/2025 | CARLOS MONTES |
| Plan Check Approved | 2/21/2025 | CARLOS MONTES |
| Issued | 2/25/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/31/2025 | CARLOS AGUILERA |
| Clean Up Green Up | Cleared | 2/11/2025 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/12/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/27/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/27/2025 | Corrections Issued | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 3/4/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 3/4/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 3/10/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 3/10/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 4/15/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/15/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 4/22/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/22/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/7/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/22/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2025 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 5/22/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 5/22/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/26/2025 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/26/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 12/26/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 12/26/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/13/2026 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/13/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 1/13/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 1/13/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/9/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/9/2026 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/9/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/9/2026 | Approved | MICHEL ABAJAN |
| Insulation | 3/25/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/25/2026 | Approved | MICHEL ABAJAN |