15057-15059 W LASSEN ST 91345
Certificate Information: 15057-15059 W LASSEN ST 91345
- Application / Permit
- 25014-20000-00169
- Plan Check / Job No.
- B25VN00812
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Portion of (E) SFD to be Converted to (450.5sq.ft) JADU per per GCS 65852.2(e)(1)(A) and 65852.22 and ground floor addition to (E) 1-Story SFD.
- Permit Issued
- Issued on 2/13/2025
- Issuing Office
- Current Status
- CofO Issued on 5/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2025 | DAVID CASTILLO |
| Corrections Issued | 1/21/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 1/30/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 2/3/2025 | DAVID CASTILLO |
| Plan Check Approved | 2/12/2025 | DAVID CASTILLO |
| Issued | 2/13/2025 | APPLICANT |
| CofO in Progress | 4/10/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 5/14/2026 | RUBEN SALAS |
| CofO Issued | 5/14/2026 | RUBEN SALAS |
| Permit Finaled | 5/14/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/23/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/23/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 1/24/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/4/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/27/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/27/2025 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 4/1/2025 | Approved | MICHAEL CORTEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 9/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 9/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/11/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 9/11/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/11/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 9/17/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/17/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/23/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 9/30/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 10/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/16/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/21/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/3/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/3/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/3/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Shower Pan | 11/3/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/10/2025 | Approved | CHRISTOPHER MORFIN |
| Shower Pan | 11/10/2025 | Approved | CHRISTOPHER MORFIN |
| BUILDING-Rough-Frame | 3/17/2026 | Approved | JENNIFER RABUCHIN |
| Final | 3/17/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/17/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 3/17/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 3/17/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 3/31/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 3/31/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/31/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 3/31/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/8/2026 | Approved | JENNIFER RABUCHIN |
| Final | 4/8/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 4/8/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 4/8/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/8/2026 | Approved | JENNIFER RABUCHIN |